Change Resource Calendar Using Bulk Edit or Not?

Home Forums Discussion Forum Change Resource Calendar Using Bulk Edit or Not?

Viewing 3 reply threads
  • Author
    Posts
    • #384709
      John Murphy
      Member

      I have about 100 resources who need to be assigned the India holidays instead of the US ones. I created the new calendar. I expected to be able to select the resources in the Resource Center and then click BULK EDIT to change the calendar for all of them in one action. However, calendar is not a field which can be changed in BULK EDIT.

      How can I make calendar BULK EDITABLE?

      Thanks
      John

    • #384710
      Anonymous
      Inactive

      Easiest way is to open them up in Microsoft Project (using the Open command in the Resource Center). Hope that helps.

    • #384749
      John Murphy
      Member

      Larry,

      YOU are the BEST!!!!!!

      Oh my, oh my … Thanks!

      John

    • #384764
      Anonymous
      Inactive

      Thank you for the kind words. Glad it helped…