Change Project TimeScale on PWA

Home Forums Discussion Forum Change Project TimeScale on PWA

Viewing 3 reply threads
  • Author
    Posts
    • #383682
      John Murphy
      Member

      When you open a project on PWA, the timescale displayed is Week – Day. Is there a way to change this like on Project Pro?

      Thanks
      John

    • #383683
      Anonymous
      Inactive

      Hi John, sorry to say there is not a way to customize the timescale setting. The timescale does change as you zoon in and out to match the Gantt chart, but this is automatic and cannot be configured.

    • #383688
      John Murphy
      Member

      Larry,

      Well I did not know the zoom had that effect! This helps!

      I still wish that you could set the default timescale on PWA.

      Thanks and HAPPY NEW YEAR!

      John

    • #383715
      Anonymous
      Inactive

      Glad it answered your question. Maybe next release…:-)