      MS Project 2010: How to apply bar styles to different views? I created some necessary bar styles but when I change views, the bar styles do not carry over.

    • #357796
      Anonymous
      Inactive

      Connie, good question. Bar styles are per view so they don’t naturally apply across views. A couple of suggestions:
      1. You might try to copy the view to another project using the organizer, rename the view, then copy the view back. That should copy the bar styles along (but I didn’t test this to be sure).
      2. Use the same view but just apply a different tables.
      Let me know what you end up doing or have any other questions. Hope this helps.