      Previous versions on MS Project had an “Adjust Dates” button used for similar schedules, but with different start dates that automatically adjust the entire schedule. Where do I find this all important function on Microsoft Project 2013?

    • #115429
      Anonymous
      Inactive

      It is now called Move Project which is in the Project ribbon.