Added Resource Vacation Time to a Project

Home Forums Discussion Forum Added Resource Vacation Time to a Project

Viewing 2 reply threads
  • Author
    Posts
    • #414421

      Hello,

      We are currently using Project Online with MS Project 2013. A Standard calendar has been created on the Project Online side and is used for all resources.
      Some of the PMs would like to add vacation time for resources as non-working time. How can this be done so that the PMs can do these changes themselves?

      Thanks.. Larry

    • #414424
      Anonymous
      Inactive

      Unfortunately not without the ability to edit enterprise resources. I’ve suggested using a special vacation project with a higher priority for customers using resource leveling. You can still use that for other customers but it won’t reduce demand for those periods. Not great news but that’s the way it works. Resources belong to the enterprise and not a particular project. Hope that helps…

    • #414425
      Norman Christensen
      Guest

      Thanks. That is what I thought.