This tip explains Lag with Dependencies other than Finish to Start, like Finish to Finish and Start to Start, in Microsoft Project 2013.
First we create a simple project:
As you can see in the Predecessors field, Tasks 1 and 2 have a Finish To Finish (FF) relationship, and Tasks 3 and 4 have Start To Start (SS) Dependencies. Now, suppose that Task 2 and Task 4 have two days of lag:
You get:
Task 2 will have a finish date of August 4, 2015 and will start two days later, so its start date is postponed!
When we repeat this for Task 4 we get:
The same result! The point to remember is that, yes, you can have Lag (and Lead) in tasks with dependencies other than Finish to Start, but be aware of consequences!
Jim Donovan
I actually prefer to put lags on SS or FF type of dependencies instead of using a FS with a Lead. However. You need to make sure you have a dependency that controls both ends of your task or the Critical Path may not be correct. Especially if you only use a SS dependency and don’t control the end of the task.
An issue I have found with using SS or FF dependencies, the Task Inspector doesn’t work the way it should. Have you also found this to be true?
great article. Thanks,