Project managers are responsible for building and updating quality project schedules. When building these schedules, it’s important to ensure they are free of potential scheduling issues. Issues can be such as the following:

  • Tasks that have not been baselined
  • Summary tasks with dependencies
  • Summary tasks with resource assignments
  • Tasks which need to be updated
  • Tasks without resource assignments
  • Milestone tasks with a duration greater than zero
  • Tasks that have negative Total Slack
  • Tasks that have an unfavorable variance and are on the project’s critical path

This article will introduce you to the creation of customizable graphical indicators that quickly and easily identify problems such as those noted above within your schedule. These techniques can be applied to standalone Microsoft Project, Project Online, and Project Server.

Using a Graphical Indicator to Identify Tasks that Have Not Been Baselined

The following steps show you how to create a custom Flag field, which will allow you to identify all tasks in your project that have not yet been baselined.

1. Open a project in Microsoft Project, right-click in the heading of any column, and from the dropdown list, click Custom Fields.

2. In the Custom Fields dialog,

a. Select the Task button, and from the adjacent dropdown list, select Flag.

b. Use the Rename… button to name your Flag field, “Tasks Not Yet Baselined.”

c. In the Custom attributes section, click Formula…

d. Complete the Formula dialog as follows, and click OK.

e. In the Custom Fields dialog, Click Graphical Indicators…

f. Complete the Graphical Indicators dialog as follows:

g. Next, select the Summary rows option, and select/set the same options as in the previous step.

h. Click OK in the Custom Fields dialog.

3. Add a new column in your project called “Tasks Not Yet Baselined.” All tasks that meet the criteria you’ve established, that is [Baseline Start] = ProjDateValue(“NA”), will have a red flag in the Tasks Not Yet Baselined column:

Interested in Learning More?

I dive deeper into this topic in my PMI® PDU eligible on-demand webinar, Using Custom Fields and Graphical Indicators to Analyze the Quality of Your Schedule. We cover how to effectively use custom fields and graphical indicators to ensure the quality of your project schedule.

Get Weekly PM Insights

Join 500,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM Glossary

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUG Logo

© 2025 MPUG. All rights reserved.

TermsPrivacySitemap
Articles

Enhancing Project Schedule Quality with Custom Graphical Indicators in Microsoft Project

Project managers are responsible for building and updating quality project schedules. When building these schedules, it’s important to ensure they are free of potential scheduling issues. Issues can be such […]

2 min read
•over 5 years ago••
I
Ira BrownAuthor
Project Management
Microsoft Project
Best Practices
Productivity
I
Ira Brown

Content Writer

Ira Brown is a leader in the field of project management and a recognized Microsoft Project expert, Project Widgets is well-known for offering add-on products for Microsoft Project and Project Online, as well as for creating custom solutions that meet their client's unique business requirements.  This company continues to extend the scope and breadth of their offerings, thereby increasing the value they provide to customers, by creating Microsoft Project solutions that are tailored to an organization's unique needs.  They even have several free, downloadable widgets available on their website that you can begin using right away.

View all articles by Ira Brown
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

Two Project Manager Agent Features You Might Like
Articles
5 min read

Two Project Manager Agent Features You Might Like

Discover two game-changing features of Microsoft’s Project Manager Agent including agent-to-agent communication and the new integrated interface in Planner.

E
Erik van Hurck
about 1 month ago
Read
Master Dependency Analysis in Microsoft Project with SSI Tools!
Articles
2 min read

Master Dependency Analysis in Microsoft Project with SSI Tools!

Learn how to master dependency analysis in Microsoft Project using SSI Tools’ Directional Path, Connecting Path, and Dependency Tracer to analyze predecessors, successors, and project logic.

K
Kenny Arnold
about 1 month ago
Read
A PM’s Halloween Survival Guide
Articles
5 min read

A PM’s Halloween Survival Guide

Discover the spooky parallels between Halloween and project management, from scope creep monsters to ghosted team members, in this fun survival guide for PMs.

R
Ronald B. Smith, MBA, PMP
2 months ago
Read
Explore All Articles