Back to ArticlesBack

Join 50,000+ PM Professionals

Get expert PM insights, PMP prep tips, and earn PDUs with exclusive content delivered weekly.

MPUG - Master Project User GroupMPUG - Master Project User Group

Background Information

A user in the Microsoft Project user forum recently asked a question about problems he was experiencing with using Expense Cost resources in his project. The user stated that when he marked a task 100% complete, the Expense Cost resource assigned to the task was not marked as complete as well.

What’s going on with this situation? Is this a bug, or is this somehow the default behavior of Microsoft Project? The answer may surprise you.

Solution

There are two scenarios involving the use of Expense Cost resources:

  1. You assign an Expense Cost resource to a task that also has Work resources assigned.
  2. You assign only an Expense Cost resource to a task.

When you enter progress in your Microsoft Project schedule, the software behaves differently in each of the two previous scenarios. For example, Figure 1 shows the Task Usage view for a project containing two tasks. Notice that Task A has both a Work resource (Mickey Cobb) and a Cost resource (Travel Expense) assigned to it. Notice that Task B has ONLY a Cost resource (Travel Expense) assigned to it.

Figure 1 – Tasks with Work and Cost resources assigned

When I mark Task A as 100% complete, notice the default behavior of Microsoft Project shown in Figure 2. For the Work resource, Mickey Cobb, the assignment is marked as 100% complete as well.  You can confirm this by the 40h value in the Actual Work column for her assignment. However, look at the Travel Expense resource. Microsoft Project DID NOT mark its assignment as 100% complete. You can confirm this by the $0.00 value in the Actual Cost column for the Travel Expense assignment. This is the behavior the user was asking about in the Microsoft Project user forum.  To fully complete this task, I must enter a value in the Actual Cost column for the Travel Expense cost resource.

Figure 2 – Task with Work and Cost resources marked complete

When I mark Task B as 100% complete, notice the default behavior of Microsoft Project shown in Figure 3. For the Cost resource, Travel Expense, this marks its assignment as 100% complete as well.  You can confirm this by the $1,850 value in the Actual Cost column for the Travel Expense assignment.

Figure 3 – Task with only a Cost resource assigned

In both of the preceding situations, you are seeing the default behavior of Microsoft Project and not a bug. This is simply how the software works with Expense Cost resources. Our job is to understand this behavior and then know how to respond when we are updating progress in our project schedules.

Get Weekly PM Insights

Join 50,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM Glossary

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUG Logo

© 2026 MPUG. All rights reserved.

TermsPrivacySitemap
Articles

Understanding the Impact of Progress on Expense Cost Resources

Background Information A user in the Microsoft Project user forum recently asked a question about problems he was experiencing with using Expense Cost resources in his project. The user stated […]

2 min read
•about 7 years ago•Updated 21 days ago•
D
Dale HowardAuthor
Project Management
Microsoft Project
Best Practices
Productivity
D
Dale Howard

Content Writer

Dale Howard is currently a Senior PPM Consultant with Arch Systems, Inc. His hair and beard have turned white because of using Microsoft's project management tools for more than 20 years. Dale started his career using Microsoft Project 4.0 for Windows 95 and began using Microsoft's PPM tools when they introduced Project Central in 2000. Dale is the co-author of 23 books in Microsoft Project, Project Server, and Project Online. He is currently one 0f 26 Microsoft Project MVPs in the entire world and one of only 4 Project MVPs in the United states.

View all articles by Dale Howard
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

How Reserves Keep Projects Alive
Articles
1 min read

How Reserves Keep Projects Alive

Learn how project reserves protect your budget and schedule from unexpected risks, including when and how to use contingency, management, schedule, and cost reserves effectively.

A
Anonymous
18 days ago
Read
Why Platform Migrations Fail (And How to Land Yours Successfully)
Articles
1 min read

Why Platform Migrations Fail (And How to Land Yours Successfully)

Learn why platform migrations fail and how to land yours successfully using proven change management tactics for PMOs facing tool transitions like Project Online’s retirement.

A
Anonymous
20 days ago
Read
Beyond Project Online: Why Now Is the Time to Plan Your Move to Modern Portfolio Management and How We Can Help
Articles
1 min read

Beyond Project Online: Why Now Is the Time to Plan Your Move to Modern Portfolio Management and How We Can Help

Microsoft Project Online retires September 2026. Learn why now is the time to plan your transition to modern portfolio management and join our free webinar on January 28.

A
Anonymous
about 1 month ago
Read
Explore All Articles