Back to ArticlesBack

Join 500,000+ PM Professionals

Get expert PM insights, PMP prep tips, and earn PDUs with exclusive content delivered weekly.

MPUG

Some time ago, one of our clients experienced an unusual situation with an enterprise project in Project Online. The client is using the Timesheet feature in Project Online to capture task progress entered on a daily basis by team members. The project contained task splits in the future, and the client could not determine why.

After studying the project in depth, I was able to determine the source of the task splits in the future. Allow me to share the results of my research with you.

Figure 1 shows a sample project that I set up to mimic the behavior the client was seeing. This figure shows the project after one week of updates were applied by the project manager. Notice the following about this project:

  • The project contains two tasks with a Duration of 20 days each. (The client was using task Durations that were much longer than 20 days).
  • These two tasks are linked with a Finish-to-Start dependency.
  • The Build task is scheduled to start on Monday, August 7.
  • The Design task has progress applied for the week of July 9. The progress was submitted by Mickey Cobb on her Timesheet in Project Web App, and this update was approved by her project manager.
  • The red dashed line is the Status date for the project, which is set to Friday of the week of July 9.
  • The green line is the Current date for the project, which is today.
  • Everything to the right of the Current date line is in the future.
  • There is nothing unusual about this project…yet.

Figure 1: Gantt Chart view before updates

Figure 2 shows the project after the project manager approved task updates from the team members for the week of July 16. Notice the following about this project:

  • The Design task has progress applied for the week of July 16. The progress was submitted by Mickey Cobb on her Timesheet in Project Web App, and this update was approved by her project manager.
  • The Build task has early progress applied to the task on Friday of the week of July 16. The team member assigned to this task reported 1 hour of Actual Work on Friday of that week. The team member submitted this progress on his Timesheet in Project Web App, and this update was approved by his project manager.
  • The early progress on the Build task created a task split that spans from last week (to the left of the Current date line) to two weeks into the future (to the right of the Current date line).
  • Microsoft Project created the task split to honor the Finish-to-Start dependency between the Design and Build tasks. Because of this, the Actual Work on the Build task is shown on Friday of the week of July 16, but the Remaining Work on this task is still scheduled to start on Monday, August 7.
  • The Duration of the Build task is now 20.88 days. This change in Duration is caused by the task split.
  • The task split in the future is normal and not a bug. Microsoft Project is working as designed.

Figure 2: Task split in the future on the Build task

If your organization uses the Timesheet feature in either Project Online or Project Server, you should be aware of the behavior documented in this blog post. There is a good possibility that you will see task splits in the future whenever you use tasks with long Durations and team members enter early progress on a task using the Timesheet in Project Web App.


Related Content

Webinars (watch for free now!):
Task Planning using Microsoft Project
What’s the value of Schedule Risk Analysis?

Articles:
Levels of Project Scheduling Proficiency
Are You Using the Team Planner View Feature in Microsoft Project?
Resource Leveling: Scheduling vs. Leveling


Get Weekly PM Insights

Join 500,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM Glossary

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUG Logo

© 2025 MPUG. All rights reserved.

TermsPrivacySitemap
Articles

Task Splits in the Future – A Scheduling Mystery

Some time ago, one of our clients experienced an unusual situation with an enterprise project in Project Online. The client is using the Timesheet feature in Project Online to capture […]

3 min read
•about 8 years ago••
D
Dale HowardAuthor
Project Management
Microsoft Project
Best Practices
Productivity
D
Dale Howard

Content Writer

Dale Howard is currently a Senior PPM Consultant with Arch Systems, Inc. His hair and beard have turned white because of using Microsoft's project management tools for more than 20 years. Dale started his career using Microsoft Project 4.0 for Windows 95 and began using Microsoft's PPM tools when they introduced Project Central in 2000. Dale is the co-author of 23 books in Microsoft Project, Project Server, and Project Online. He is currently one 0f 26 Microsoft Project MVPs in the entire world and one of only 4 Project MVPs in the United states.

View all articles by Dale Howard
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

Two Project Manager Agent Features You Might Like
Articles
5 min read

Two Project Manager Agent Features You Might Like

Discover two game-changing features of Microsoft’s Project Manager Agent including agent-to-agent communication and the new integrated interface in Planner.

E
Erik van Hurck
about 2 months ago
Read
Master Dependency Analysis in Microsoft Project with SSI Tools!
Articles
2 min read

Master Dependency Analysis in Microsoft Project with SSI Tools!

Learn how to master dependency analysis in Microsoft Project using SSI Tools’ Directional Path, Connecting Path, and Dependency Tracer to analyze predecessors, successors, and project logic.

K
Kenny Arnold
about 2 months ago
Read
A PM’s Halloween Survival Guide
Articles
5 min read

A PM’s Halloween Survival Guide

Discover the spooky parallels between Halloween and project management, from scope creep monsters to ghosted team members, in this fun survival guide for PMs.

R
Ronald B. Smith, MBA, PMP
2 months ago
Read
Explore All Articles