Back to ArticlesBack

Join 50,000+ PM Professionals

Get expert PM insights, PMP prep tips, and earn PDUs with exclusive content delivered weekly.

Protected by reCAPTCHA: Privacy & Terms

MPUG - Master Project User GroupMPUG - Master Project User Group

headache-388870_960_720Tom Henry a senior consultant at Campana & Schott, spends his weeks implementing enterprise project management systems for clients in multiple segments and training them on how to get the most out of their solutions. During the Microsoft Project Virtual Conference 2016, which ran in February, 2016, Henry shared “tips, tricks and scheduling best practices with Microsoft Project.” MPUG also asked him for a brief preview.

MPUG: Tell us something about scheduling that we may never have thought of.

Tom Henry: It gives you clear insight into projects. If you think about it, when you’re running a project, you probably have a hundred things you’re thinking about all at the same time. You may have written them down, but you can’t truly understand when these things can physically take place.

By using a scheduling tool and inputting all the tasks into a project schedule and then putting logical ties between the tasks within the project and letting Microsoft Project schedule everything out for you, so you can really get clear insight into when things can possibly happen. You gain insight you couldn’t possibly have worked out in your head. If something changes, you can input that into Project. It tells you what’s affected and what things are now going to have to be pushed, and you can take corrective action accordingly.

Where do you like to advise clients to start when they’re building a schedule, and does that vary depending on the project?

I always say to people, keep it very simple. This is a project schedule; it is not the actual project. This should be a model of the project, and a model is usually a simplified version of something. Make sure it’s concise. Put as much information as you need, but as little information as you can get away with. Don’t try to micromanage things within the schedule. Keep it high level so you can understand it and it helps you.

We’re curious. How long does it take you to build a typical project schedule?

It depends on how big it is, but typically about an hour.

That quickly?

Yeah. But I’ve been doing this for five years. And I’m usually doing repeatable projects. If I were doing something from scratch, it might take longer, where I really have to think about all the different steps and things I might not have thought of before.

When the project schedule is off track, where do you advise people to begin their forensic work to uncover the source of the problems?

When a project is off track, what you need to do is take a look at the baseline. Within Project use a table view to see a whole bunch of different columns showing you what the variance is on each task. That tracking table will show you where you’re ahead of schedule and where you’re behind. From there, you take corrective action.

Image Source

Get Weekly PM Insights

Join 50,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

Protected by reCAPTCHA: Privacy & Terms

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM Glossary

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUG Logo

© 2026 MPUG. All rights reserved.

TermsPrivacySitemapAdvertise
Articles

Scheduling Master Tom Henry on Why We Shouldn’t Run Projects in Our Heads

Tom Henry a senior consultant at Campana & Schott, spends his weeks implementing enterprise project management systems for clients in multiple segments and training them on how to get the […]

3 min read
•about 10 years ago•Updated about 2 months ago•
D
Dian SchaffhauserAuthor
Project Management
Microsoft Project
Best Practices
Productivity
D
Dian Schaffhauser

Content Writer

Dian Schaffhauser is MPUG's editor. She's been covering project management, business transformation and topics technical as a journalist and editor since IBM released its first PC. She invites you to send your best story ideas for MPUG to her at editor@mpug.com. She promises to let you know what she really thinks.

View all articles by Dian Schaffhauser
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

Your Project Online Migration Questions, Answered: Key Takeaways from Ira Brown
Articles
1 min read

Your Project Online Migration Questions, Answered: Key Takeaways from Ira Brown

Ira Brown, president of Project Widgets, breaks down the four realistic migration paths, key deadlines, and a pre-migration inventory checklist to help your organization plan ahead of the September 2026 Project Online retirement.

A
Anonymous
12 days ago
Read
The Compass vs. The Clock: Why Direction Beats Deadlines in Project Management
Articles
1 min read

The Compass vs. The Clock: Why Direction Beats Deadlines in Project Management

Discover why setting clear project direction matters more than chasing deadlines, and how compass-guided leadership delivers real value in project management.

A
Anonymous
23 days ago
Read
The Scripts That Save Projects: What to Say When Everything Goes Wrong
Articles
1 min read

The Scripts That Save Projects: What to Say When Everything Goes Wrong

Learn word-for-word scripts for handling scope creep, missed deadlines, executive pushback, and team performance issues as a project manager.

A
Anonymous
24 days ago
Read
Explore All Articles