Many projects require task scheduling in terms of physical volumes (i.e. material resources in MS Project like ten meters, five tons, twenty items, etc.). Unfortunately, Microsoft Project does not hav...
Background There was a really interesting scheduling question posted recently in the Tech Community user forum on Microsoft Project. Although I was not the one who answered the question, I thought it ...
Background Information In my third and previous article in this series, I demonstrated how the use of Deadline dates can negatively impact the Total Slack calculations for tasks in your Microsoft Proj...
Background Information The other day I had an interesting conversation with a colleague about the impact of Deadline dates on Critical Path calculations. He told me that several of his clients are hes...
Background Information In my first MPUG post about the Deadline dates feature in Microsoft Project, I documented how to set a Deadline date on a task to specify the “target” date for when that task ne...
In my recent Tracking Starts with a Status Date article, a four-step tracking cycle was defined. It includes setting the status date, entering actuals, rescheduling incomplete work, and resource level...
There are four steps involved in tracking a project: setting the status date, entering actuals and schedule revisions, rescheduling incomplete work, and resource leveling the remaining schedule. Thes...
Manually Checking for Un-baselined Tasks How do you know whether a task has been baselined in a Microsoft Project schedule? The direct way to determine if a task has been baselined is to apply any tas...
Doing the Impossible In 2010, I attended a Baltimore MPUG meeting that changed my life. I learned about Visual Basic for Applications (VBA) for Microsoft Project, and I was stunned to discover easily-...