Background

One minor issue I have with Microsoft Project is that it places the split bar to the right of the Resource Names column by default every time I launch the software and create a new blank project, such as shown in Figure 1. I would prefer that the software dock the split bar on the right edge of the Duration column instead, so that I do not need to manually set the split bar location every time I create a new blank project.

Figure 1: Split bar in the wrong location

Solution

To place the split bar in a specific location for every new blank project you create, complete the following steps:

1. Launch Microsoft Project and create a new blank project.

2. Apply the Gantt Chart view, if not already applied.

3. Drag the split bar in the location where you want to see it in every new blank project, such as docked on the right side of the Duration

4. Click the File tab and then click the Info tab in the Backstage.

5. On the Info page of the Backstage, click the Organizer button to display the Organizer

6. On the View page of the Organizer dialog, select the Gantt Chart item on the right side of the dialog (in the active project), and then click the << Copy button to copy the view to the left side of the dialog (into the Global.mpt file).

Figure 2: Organizer dialog

7. When prompted in a confirmation dialog about overwriting the Gantt Chart view in the Global.mpt file, such as shown in Figure 3, click the Yes

Figure 3: Confirmation dialog

8. Click the Close button to close the Organizer

9. Press the Escape key on your computer keyboard to exit the Backstage.

The next time you create a new blank project, Microsoft Project will dock the split bar exactly where you want to see it. For example, Figure 4 shows a new blank project I created after completing the preceding set of steps. Notice that the software correctly docked the split bar on the right edge of the Duration column as I wanted.

Figure 4: Split bar docked in correct location

Get Weekly PM Insights

Join 50,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

Protected by reCAPTCHA: Privacy & Terms

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM GlossaryOur Faculty

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUGMaster Project User Group

© 2026 MPUG. All rights reserved.

TermsPrivacySitemapAdvertise
Articles

Microsoft Project Quick Tip: Set the Split Bar Location for All New Blank Projects

Background One minor issue I have with Microsoft Project is that it places the split bar to the right of the Resource Names column by default every time I launch […]

2 min read
•over 6 years ago•Updated 10 months ago•
D
Dale HowardAuthor
Project Management
Microsoft Project
Best Practices
Productivity
D
Dale Howard

Content Writer

Dale Howard is currently a Senior PPM Consultant with Arch Systems, Inc. His hair and beard have turned white because of using Microsoft's project management tools for more than 20 years. Dale started his career using Microsoft Project 4.0 for Windows 95 and began using Microsoft's PPM tools when they introduced Project Central in 2000. Dale is the co-author of 23 books in Microsoft Project, Project Server, and Project Online. He is currently one 0f 26 Microsoft Project MVPs in the entire world and one of only 4 Project MVPs in the United states.

View all articles by Dale Howard
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

Collaboration challenges in remote projects (and how to fix each one)
Articles
1 min read

Collaboration challenges in remote projects (and how to fix each one)

Discover 5 common remote project collaboration challenges, from knowledge silos to unclear ownership, and learn practical ways to keep teams aligned and work moving.

A
Anonymous
5 days ago
Read
An Introduction to the PMI Practice Standard for Scheduling Conformance Index
Articles
1 min read

An Introduction to the PMI Practice Standard for Scheduling Conformance Index

Learn how the Conformance Index in PMI’s Practice Standard for Scheduling scores a CPM schedule model, and how to assess its components in any scheduling tool.

A
Anonymous
17 days ago
Read
A PM’s Halloween Survival Guide: The Sequel You Didn’t Want but Definitely Need
Articles
1 min read

A PM’s Halloween Survival Guide: The Sequel You Didn’t Want but Definitely Need

Part II of the PM Halloween survival guide takes on shape-shifting requirements and dependencies that won’t stay resolved, with practical defenses for each.

A
Anonymous
about 1 month ago
Read
Explore All Articles