Are you already using the Holiday Calendar feature in MS Project? If you aren’t or you want to learn more about how to make your schedule more accurate, keep reading! The default “holiday calendar” in MS Project is called “Standard” (see Fig 1), and actually has no holidays in it (see Fig 2). If it did, it would look like Fig 3.

Figure 1: Default Project Creation

Figure 2: Default “Standard” Calendar

Figure 3: Example Holiday Calendar Entries

The official list of US Federal Holidays is provided here: Federal Holidays (opm.gov). There are 11, including the recent addition of Juneteenth. That’s more than two weeks’ worth of non-work days! If you aren’t using a holiday calendar in MS Project, your schedule could be off by two weeks at any given time. In addition to holidays, most staff take a day of vacation on the Friday after Thanksgiving, as well as take time off during the period between Christmas Day and New Year’s Day.

Given all this, the holiday calendar is error-prone and a pain to construct. Some holidays have a fixed-date which requires re-jiggering for the preceding Friday or succeeding Monday when such a holiday falls on a weekend. Other holidays have fixed days such as “the fourth Thursday in November.” This requires determining the actual date each year. There are 340 such calendar entries in the years spanning 2020-2050.

I’m a passionate believer in the holiday calendar. Newly-retired and motivated by the recent addition of Juneteenth, I attacked the construction and I’ve now created a “strict” calendar version that includes only the official federal holidays, as well as a “realistic” calendar version that also includes the Friday after Thanksgiving and the entire period from Christmas Eve through New Year’s Day. I recommend using the latter—no one will criticize you for avoiding scheduling events during Christmas break. Note that a holiday calendar does not prevent staff from working—it just avoids scheduling on certain dates.

You can obtain a template file containing both calendar versions from the website MSProjectHolidayCalendars.com. There is a $10 fee.  These calendars were auto-generated using custom code plus some manual editing, so they are quite reliable.  I’d love to hear from you in the comments below if you try it.

Get Weekly PM Insights

Join 50,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

Protected by reCAPTCHA: Privacy & Terms

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM GlossaryOur Faculty

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUGMaster Project User Group

© 2026 MPUG. All rights reserved.

TermsPrivacySitemapAdvertise
Articles

Microsoft Project Holiday Calendars 2020-2050 Available for Download

Are you already using the Holiday Calendar feature in MS Project? If you aren’t or you want to learn more about how to make your schedule more accurate, keep reading! […]

2 min read
•over 5 years ago•Updated 10 months ago•
J
Jim PeterAuthor
Project Management
Microsoft Project
Best Practices
Productivity
J
Jim Peter

Content Writer

Jim Peter is a retired engineering planner with over three decades of experience in project planning and scheduling. He has a BS in Electrical Engineering, and MS in Computer Science, and an MS in Technical Management. He has written numerous custom VBA macros in MS Project. He is a native and resident of Baltimore. See the availability of MS Project Holiday Calendars here.

View all articles by Jim Peter
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

Collaboration challenges in remote projects (and how to fix each one)
Articles
1 min read

Collaboration challenges in remote projects (and how to fix each one)

Discover 5 common remote project collaboration challenges, from knowledge silos to unclear ownership, and learn practical ways to keep teams aligned and work moving.

A
Anonymous
9 days ago
Read
An Introduction to the PMI Practice Standard for Scheduling Conformance Index
Articles
1 min read

An Introduction to the PMI Practice Standard for Scheduling Conformance Index

Learn how the Conformance Index in PMI’s Practice Standard for Scheduling scores a CPM schedule model, and how to assess its components in any scheduling tool.

A
Anonymous
20 days ago
Read
A PM’s Halloween Survival Guide: The Sequel You Didn’t Want but Definitely Need
Articles
1 min read

A PM’s Halloween Survival Guide: The Sequel You Didn’t Want but Definitely Need

Part II of the PM Halloween survival guide takes on shape-shifting requirements and dependencies that won’t stay resolved, with practical defenses for each.

A
Anonymous
about 1 month ago
Read
Explore All Articles