You know that Microsoft Project is a great scheduling tool. Did you also know that it can help you quantify and evaluate risk?

In this article, I will provide you with the basics for a simple risk evaluation tool. Then, in my article next week, I will build a Risk Assessment Dashboard in Microsoft Project.

Risk severity is usually expressed in terms of probability and impact to a task or a project’s product, schedule, work or cost. When used to mathematically indicate risk severity, the formula is:

Risk Severity = Probability X Impact

The grid below is a model to group and evaluate task and project risk. Risks are represented on a scale of 1 (low) to 25 (high) and are the result of the severity formula.

riskassessmentdash_1

In this simplified model, I arbitrarily identified and grouped risks according to the following rules:

riskassessmentdash_2

Naturally, your organization would need to decide on the value range representing high, medium, and low risk.

The purpose of evaluating the risk is to determine if any action is needed to mitigate or retire the risk. In my model, low risks are only monitored. Medium risks are monitored and a mitigation plan created but not executed. A high risk receives action for retirement.


Want more Do’s and Don’ts? Check out MPUG’s new book: Microsoft® Project Do’s and Don’ts!


Risk assessments range from simple spreadsheets (like my example), to complicated programs creating statistical forecasts and representative graphics. The key is that you have a tool that is useful and usable for you in the management of risks.

In the next article I will outline the steps to create a Risk Assessment Dashboard. It looks like the figure below and will provide at a glance the rules, mathematical formula and graphics to alert you to the state of risk in your project.

riskassessmentdash_3

Get Weekly PM Insights

Join 50,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

Protected by reCAPTCHA: Privacy & Terms

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM Glossary

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUG Logo

© 2026 MPUG. All rights reserved.

TermsPrivacySitemapAdvertise
Articles

Microsoft® Project Do’s and Don’ts: Creating a Risk Assessment Dashboard: Part 1

You know that Microsoft Project is a great scheduling tool. Did you also know that it can help you quantify and evaluate risk? In this article, I will provide you […]

2 min read
•over 11 years ago•Updated 3 months ago•
S
Sam HuffmanAuthor
Project Management
Microsoft Project
Best Practices
Productivity
S
Sam Huffman

Content Writer

Sam Huffman first gained insight into Microsoft Project while working as a member of the MS Project development and support team. He has maintained his depth of knowledge of MS Project with each release and is a leading authority in the use and features of MS Project, Project Server and Project Online. Since the early 1990's Sam has honed his instruction skills by delivering training programs to thousands every year. Sam is a frequent content contributor to the Microsoft Project User Group (MPUG) and speaks to groups often about MS Project, Enterprise Project Management and the discipline of Project Management. He was awarded Microsoft Most Valuable Professional from 2010-2017. Check out his blog on MS Project. The softcover version of my newest book Microsoft® Project Do’s and Don’ts is now available for purchase! It is portable, brief and to the point so you can find help when you need it. Through tips, best practices and examples it will help you jumpstart your project!

View all articles by Sam Huffman
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

Are You Running a Risk Meeting or a Risk Workshop?
Articles
1 min read

Are You Running a Risk Meeting or a Risk Workshop?

Learn the difference between a risk meeting and a risk workshop, and why structured risk workshops help project teams identify owners, define actions, and protect project outcomes.

A
Anonymous
about 20 hours ago
Read
“I Need a Dashboard by Friday” – How AI Just Made That Possible
Articles
1 min read

“I Need a Dashboard by Friday” – How AI Just Made That Possible

Need a dashboard by Friday? Discover how AI tools like ChatGPT can help you build an Excel dashboard quickly and easily—no advanced technical skills required. Learn how to turn plain-English requests into real, working reports with spreadsheets that actually work for you.

A
Anonymous
about 20 hours ago
Read
Why Tools Matter More Than Ever in Project Management (And Why Most Organizations Still Get Them Wrong)
Articles
1 min read

Why Tools Matter More Than Ever in Project Management (And Why Most Organizations Still Get Them Wrong)

Most PPM tools fail because they’re built for oversight, not adoption. Here’s how to design for decisions instead, and why Smartsheet bridges the gap.

A
Anonymous
3 days ago
Read
Explore All Articles