Back to ArticlesBack

Join 50,000+ PM Professionals

Get expert PM insights, PMP prep tips, and earn PDUs with exclusive content delivered weekly.

Protected by reCAPTCHA: Privacy & Terms

MPUG - Master Project User GroupMPUG - Master Project User Group

Have you ever set up a new project and gotten stuck with default calendars you didn’t really want? In the following short article and my upcoming webinar, I will show you how to fix unexpected calendar issues and what precautions should be taken. Let’s consider a default setup for Working hours per day in Microsoft Project for the Web. Here is my Project:

What’s next? Well, let me create one task with an eight-day duration. See the figure below:

As you can see, our task will start on Monday, 4/5/2020, and finish on Monday, 4/12/2020. Notice that it will be performed during the weekend, as well.

Now I will create three Tasks: Task 7 hours, Task 8 Hours, and Task 9 hours, with durations as show in the figure below:

As you can see, one day is eight hours. In Task 9 hours, the Finish date is 4/6/2020, and the Start date is 4/5/2020, In Task 8 hours, the Finish date is 4/5/2020, and the Start date is 4/5/2020.

How is it so, and what if I want that my days to cover nine hours, but only from Monday to Friday? The default value is that our task is starting from 09:00 AM and finishing at 05:00 PM. To see that, I’ve used Dynamics 365:

and:

and finally:

Now I will show you default working time. To do that, navigate to settings:

And then to Calendar Templates:

The result is shown below:

Project for the Web uses this default template if I do not define another, but I can create a new template with working hours from 09:00 AM to 06:00 PM, during working days. To accomplish that, first I have to create a resource with those working hours. I will call this Generic Resource.

To do this, first, go to the Resource page in Dynamics 365:

And then:

Finally, I will create the new Resource:

Now, set up working time as outlined below.

Step 1:

Step 2:

Step 3:

Step 4:

Step 5:

Since those working hours are valid only until 3/28/2020, I will repeat my steps as shown:

And:

Finally:

OK, now we must go back to the Settings:

And:

And, then:

I will call my template: Weekdays Calendar from 09:00 AM to 06:00 PM:

OK. I am done here! Now I will create a brand new Project for the Web:

Task has an eight-day duration, and Task 7 hours, Task 8 hours, Task 9 hours, and Task 10 hours as shown:

As you can see, Task (with the eight day duration) is now showing as going to be finished on 4/15/2020, which is a Wednesday (Saturday and Sunday are no longer counted as working hours). You can also see that duration of one day is nine hours, not eight anymore!

Complicated? Maybe. Powerful? Oh, yes!

As I started out by sharing, Project calendars and resource Calendars are important for every Project. In Microsoft Project for the Web, they can be defined, but not like in the Project Desktop or Online versions. When using Project for the Web, calendars are available using Dynamics 365 / PowerApps. To learn more than this article outlines, check out my on-demand webinar.

Get Weekly PM Insights

Join 50,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

Protected by reCAPTCHA: Privacy & Terms

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM Glossary

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUG Logo

© 2026 MPUG. All rights reserved.

TermsPrivacySitemapAdvertise
Articles

Mastering Calendar and Working Hours in Microsoft Project for the Web

Have you ever set up a new project and gotten stuck with default calendars you didn’t really want? In the following short article and my upcoming webinar, I will show […]

3 min read
•over 5 years ago•Updated 3 months ago•
N
Nenad TrajkovskiAuthor
Project Management
Microsoft Project
Best Practices
Productivity
N
Nenad Trajkovski

Content Writer

MVP - Project Nenad Trajkovski was born in Zagreb in 1963. year. After completion of Faculty of Electrical Engineering, Nenad has started on the development and implementation of enterprise systems (ERP) in companies of various areas (banks, card houses, production companies, auto industry, wholesale businesses, oil companies, and others). He has extensive experience in working with business processes, people and knowledge in information technology and financial accounting activities. Currently, Nenad works as a consultant for the implementation of business systems, and as Project Manager. He is trainer for Project Management and Risk Management in Microsoft Innovation Center in Varaždin. At WinDays08 conference he has been declared as the best speaker, and his session as the best one. He was among TOP 10 speakers in the Microsoft Sinergija 2009 and at the Microsoft Vzija 2009. Shared first place as the best lecturer at KulenDays 2009 and the PMI Forum 2009 in Zagreb. Regular speaker at the Microsoft Community. On WinDays10 conference Nenad was among the top three speakers; at the conference Microsoft Vision 9 in Skopje between the top 5 speakers as well as on Microsoft Synergy 11 which was held in Belgrade. Certified Accountant, PMP (Project Manager Professional), PMI – RMP (Risk Manager Professional), MCP (Microsoft Certified Professional), MCTS – Microsoft Project 2010 (Microsoft Certified Technical Professional).  and MCT (Microsoft Certified Trainer).

View all articles by Nenad Trajkovski
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

Are You Running a Risk Meeting or a Risk Workshop?
Articles
1 min read

Are You Running a Risk Meeting or a Risk Workshop?

Learn the difference between a risk meeting and a risk workshop, and why structured risk workshops help project teams identify owners, define actions, and protect project outcomes.

A
Anonymous
2 days ago
Read
“I Need a Dashboard by Friday” – How AI Just Made That Possible
Articles
1 min read

“I Need a Dashboard by Friday” – How AI Just Made That Possible

Need a dashboard by Friday? Discover how AI tools like ChatGPT can help you build an Excel dashboard quickly and easily—no advanced technical skills required. Learn how to turn plain-English requests into real, working reports with spreadsheets that actually work for you.

A
Anonymous
2 days ago
Read
Why Tools Matter More Than Ever in Project Management (And Why Most Organizations Still Get Them Wrong)
Articles
1 min read

Why Tools Matter More Than Ever in Project Management (And Why Most Organizations Still Get Them Wrong)

Most PPM tools fail because they’re built for oversight, not adoption. Here’s how to design for decisions instead, and why Smartsheet bridges the gap.

A
Anonymous
4 days ago
Read
Explore All Articles