Back to ArticlesBack

Join 50,000+ PM Professionals

Get expert PM insights, PMP prep tips, and earn PDUs with exclusive content delivered weekly.

MPUG - Master Project User GroupMPUG - Master Project User Group

The Background Story…

I have been a project manager for over forty years. Over that time, I got into the habit of checking my projects for late starts and finishes two or three times a month. This would help me to flag task problems that I needed to research and try to get back on schedule. Originally, I would take my plan and sort the % Complete field which gave me three major groups: 0% (Not Started), 1% – 99% (Started), and 100% (Completed). My initial focus was to drill-down on the first two groups and highlight potential task problems. For the first group (Not Started), I would highlight the tasks that had a start date that was less than or equal to the current date at that time. Keep in mind these late starting tasks could eventually turn in late tasks. For the second group (Started), I would highlight the tasks that had a finish date that was less than or equal to the current date. On large projects, this exercise was time-consuming, and I felt like a kid using a flashlight at night as I drilled-down to find tasks that had late starts and finishes.

Highlighting A Better Way

Within Microsoft Project, there are multiple ways to find tasks that have late starts and finishes. They include using multiple filters, reports, and/or using a macro. I typically chose to use a simple filter to meet my needs, and Figure 1 below shows a small project plan that I will use to demonstrate my approach using highlighting. Applying a routine filter hides information that does not meet your criteria and applying a highlight (a yellow format) to information that does meet your criteria. Otherwise, the two approaches are nearly identical. When a highlight is applied, the Highlight Filter Applied message appears on the bottom left side of the status bar.

Figure 1: Project Plan

To create this new filter, go to the View tab > Data section > Highlight’s drop-down menu > More Highlight Filters > New (Figure 2). To see the result, reference Figure 3. Initially name your filter (e.g., Late Starts and Finishes) and define your filter logic. For the first line, I didn’t use % Complete because it represents the duration that is complete, not the progress that’s been completed on the work. Instead, I used the more accurate % Work Complete ((Actual Work/Work) x 100)) that equals 0% And (logic operator) Start that is less than or equal to “Enter status date:?” (interactive prompt for later) to find the late starts.

Figure 2: More Filters Dialog Box

Figure 3: Filter Definition Dialog Box

Next, I used the Or (logic operator) Status that equals Late to find the late finishes. There are four types of Status – Late, Complete, On Schedule, or Future Tasks. When finished, click Save. Then click Highlight from Figure 2. When you select this filter from the Highlight pull-down arrow, the interactive “Enter status date:” dialog box will pop-up (Figure 4) for you to enter the selected date and click OK. This brings you to Figure 5, where you can now see the highlighted late start and finish tasks. You can tell from the % Work Complete column that the task IDs 1 and 6-7 are late finishes (> 0%) and the task IDs 13-14 are late starts (= 0%).

Figure 4: Enter Status Date Dialog Box

Figure 5: Highlighted Late Starts and Finishes

Summary

Using filters to create your specific information requirements can be extremely helpful. This coupled with using the already built-in filters can up your game as a project manager. Sometimes, you might copy a built-in filter as a foundation for creating your own. Your comments on this topic are appreciated below.

Get Weekly PM Insights

Join 50,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM Glossary

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUG Logo

© 2026 MPUG. All rights reserved.

TermsPrivacySitemap
Articles

Late Tasks: Starts and Finishes

The Background Story… I have been a project manager for over forty years. Over that time, I got into the habit of checking my projects for late starts and finishes […]

3 min read
•about 4 years ago•Updated 17 days ago•
R
Ronald B. Smith, MBA, PMPAuthor
Project Management
Microsoft Project
Best Practices
Productivity
R
Ronald B. Smith, MBA, PMP

Content Writer

Ronald Smith has over four decades of experience as Senior PM/Program Manager. He retired from IBM having written four books and over one hundred articles on project management, and the systems development life cycle (SDLC). He’s been a member of the Project Management Institute (PMI) since 1998, which has a membership of about 3 million professionals worldwide. From 2011 - 2017, Ronald had been an Adjunct Professor for a Master of Science in Technology and taught PM courses at the University of Houston’s College of Technology. Teaching from his own book, Project Management Tools and Techniques – A Practical Guide, Ronald offers a unique perspective on project management that reflects his many years of experience. Besides writing, he swims five times a week to keep in shape. Lastly in the Houston area, he has started up two Toastmasters clubs and does voluntary work at various food banks to help people facing hunger.

View all articles by Ronald B. Smith, MBA, PMP
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

How Reserves Keep Projects Alive
Articles
4 min read

How Reserves Keep Projects Alive

Learn how project reserves protect your budget and schedule from unexpected risks, including when and how to use contingency, management, schedule, and cost reserves effectively.

R
Ronald B. Smith, MBA, PMP
13 days ago
Read
Why Platform Migrations Fail (And How to Land Yours Successfully)
Articles
4 min read

Why Platform Migrations Fail (And How to Land Yours Successfully)

Learn why platform migrations fail and how to land yours successfully using proven change management tactics for PMOs facing tool transitions like Project Online’s retirement.

T
The MPUG Community
16 days ago
Read
Beyond Project Online: Why Now Is the Time to Plan Your Move to Modern Portfolio Management and How We Can Help
Articles
5 min read

Beyond Project Online: Why Now Is the Time to Plan Your Move to Modern Portfolio Management and How We Can Help

Microsoft Project Online retires September 2026. Learn why now is the time to plan your transition to modern portfolio management and join our free webinar on January 28.

T
The MPUG Community
27 days ago
Explore All Articles
Read