Finish-to-Start Relationships

Insights for SchedulingThe finish-to-start relationship states that one task must be completed before its successor task can begin. The network diagrams in this chapter all follow this simple assumption because it is the most common, but there are other types of relationships. Tasks with start-to-start (SS) relationships allow the successor task to begin when the predecessor task begins. Finish-to-finish (FF) tasks can start independently of each other, but the successor cannot finish until the predecessor finishes. The figures below show the value of using these other types of relationships.

Finish-to-start: The most common task relationships on the network are finish-to-start. The first task must finish before the next one can start.

Insights for Scheduling
Start-to-start: The successor task can start as soon as the predecessor task starts. The example shows a painting company, painting all the rooms on one floor of an office building. After the first room is prepared, both the prep crew and the paint crew can begin working at the same time. Overlapping the tasks reduces the total duration of the project.

Insights for Scheduling

Finish-to-finish: The successor task can finish only when the predecessor task is finished. The example shows the last two tasks of a design phase. Planning for the construction phase can begin before the final design approval, but it cannot finish until the design is complete.

Insights for Scheduling

Understanding Float

Almost every critical path schedule has float. There are actually four kinds of float that can occur in a schedule.

  • Total float = Late start minus early start (LS-ES).
  • Free float = Float that doesn’t affect subsequent activities.
  • Independent float = Free float that cant be used by earlier activities.
  • Shared float = Float that belongs to a path, rather than a single task.

This article is excerpted from the new book, The Fast Forward MBA in Project Management, 4th Edition. Copyright 2011. This material is used by permission of John Wiley & Sons, Inc.

Get Weekly PM Insights

Join 50,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

Protected by reCAPTCHA: Privacy & Terms

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM Glossary

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUG Logo

© 2026 MPUG. All rights reserved.

TermsPrivacySitemapAdvertise
Articles

Insights for Scheduling

Finish-to-Start Relationships The finish-to-start relationship states that one task must be completed before its successor task can begin. The network diagrams in this chapter all follow this simple assumption because […]

2 min read
•almost 14 years ago•Updated 3 months ago•
E
Eric VerzuhAuthor
Project Management
Microsoft Project
Best Practices
Productivity
E
Eric Verzuh

Content Writer

Eric Verzuh, PMP, earned his PMP in 1992. He is the author of the bestselling Fast Forward MBA in Project Management and the PMP® Deep Dive, a better, faster, and more fun exam prep program. You can contact Eric via email at EVerzuh@VersatileCompany.com.

View all articles by Eric Verzuh
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

Are You Running a Risk Meeting or a Risk Workshop?
Articles
1 min read

Are You Running a Risk Meeting or a Risk Workshop?

Learn the difference between a risk meeting and a risk workshop, and why structured risk workshops help project teams identify owners, define actions, and protect project outcomes.

A
Anonymous
about 19 hours ago
Read
“I Need a Dashboard by Friday” – How AI Just Made That Possible
Articles
1 min read

“I Need a Dashboard by Friday” – How AI Just Made That Possible

Need a dashboard by Friday? Discover how AI tools like ChatGPT can help you build an Excel dashboard quickly and easily—no advanced technical skills required. Learn how to turn plain-English requests into real, working reports with spreadsheets that actually work for you.

A
Anonymous
about 19 hours ago
Read
Why Tools Matter More Than Ever in Project Management (And Why Most Organizations Still Get Them Wrong)
Articles
1 min read

Why Tools Matter More Than Ever in Project Management (And Why Most Organizations Still Get Them Wrong)

Most PPM tools fail because they’re built for oversight, not adoption. Here’s how to design for decisions instead, and why Smartsheet bridges the gap.

A
Anonymous
3 days ago
Read
Explore All Articles