Back to ArticlesBack

Subscribe to our newsletter

Get the latest articles and resources sent straight to your inbox.

MPUG

These tips and traps from a project management and scheduling expert cover the essence of project scheduling, framing the workday properly and handling out-of-scope requests.

No Dates

When you schedule electronically, you should not enter start of finish dates for tasks. If you use Microsoft Project to simply capture dates and only dates, you may as well use Microsoft Excel instead. With Project, you enter durations and dependencies instead of dates to create a forecast model. The software then calculates start and finish dates by itself, based on those durations and dependencies. A schedule with dependencies knows how to update other tasks automatically and is a dynamic model. We have started to call this the 4D-1D approach to scheduling: Deliverables, Durations, Dependencies and Deadlines, but no Dates. Entering dates on Auto Scheduled tasks leads to rigid schedules with many constraint dates.

Hours per Day Conversion Factor

Before entering any tasks, you have to specify how many work hours equal a workday by using option Hours per Day on the tab Schedule (ribbon File, item Options). Project uses this setting to convert between time units; it is the time unit conversion factor. All durations will be recalculated when you change this option. For example, if Hours per Day is set to eight hours and you enter a duration of five days, Project knows this equals:

8 * 5 = 40 hours

If you then change Hours per Day from eight to seven, Project changes this duration to 5.71 days:

(= 5 * 8 / 7)

If you start with the wrong conversion factor, Project will interpret durations you enter incorrectly, which may result in a schedule that is too low or high in its forecasts.

Tip: There is a workaround to keep the current durations without having to re-enter all durations when you change the Hours per Day setting. Before changing Hours per Day, copy all durations to one of the extra text fields (Text1, for example), then change Hours per Day. Make sure you have task field Type set to Fixed Units for all tasks to ensure that Project does not change resource assignments. Then copy the durations from Text1 back into the Duration field.

Tip! There is an Auto Save option that saves your schedule every so many minutes, which you can select in ribbon File, item Options, tab Save. Trap! Note that each Auto Save wipes out the list of items you can Undo, therefore, you should carefully consider if you want to turn on auto saving (default is off).

Out of Scope

Capture out-of-scope elements in a note on the project summary task (ribbon Format, check Project Summary Task) using the Notes tool (Task ribbon). We recommend paying careful attention to clarifying what is in-scope and out-of-scope to manage the expectations of your client carefully and early in the life of the project. Creating a detailed work breakdown structure (WBS) and list of out-of-scope deliverables with your client’s agreement ensures that you have had a veritable meeting of the minds with the client, the essence of a contract.

Trap! Also, realize that many team members will happily live with a vaguely formulated WBS, and it will not work as a contract for them either. They may choose to fly under the radar and not be accountable.

This content originally appeared in Eric Uyttewaal’s book, Forecast Scheduling with Microsoft Project 2013: Best Practices for Real-World Projects. Learn more on the Project Pro website here.

Have your own tips? Share them with the MPUG community in comments below.

Get Weekly PM Insights

Join 500,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM Glossary

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUG Logo

© 2025 MPUG. All rights reserved.

TermsPrivacySitemap
Articles

Good Project Advice

These tips and traps from a project management and scheduling expert cover the essence of project scheduling, framing the workday properly and handling out-of-scope requests. No Dates When you schedule […]

3 min read
•over 8 years ago••
E
Eric UyttewaalAuthor
Project Management
Microsoft Project
Best Practices
Productivity
E
Eric Uyttewaal

Content Writer

Eric is a thought leader on project, program, and portfolio management. He spends most of his time using software from Microsoft. He has authored seven well-known textbooks including ‘Forecasting Programs,’ 'Forecast Scheduling with Microsoft Project 2010/2013/Online,’ and ‘Dynamic Scheduling with Microsoft Project 2000/2002/2003.’ He founded ProjectPro, which specializes in Microsoft Project, Project Server and Project Online. Eric developed several Add-ins with his team that enhance the capabilities of Microsoft Project in creating better schedules (Forecast Scheduling App), managing cross-project dependencies (CrossLinksPro), identifying and documenting the Critical Path (PathsPro) and creating S-curve reports (CurvesPro). He was president of PMI-Ottawa in 1997. Eric has received awards from PMI in 2009, from MPUG in 2012, and from Microsoft from 2010 until 2017 (MVP).

View all articles by Eric Uyttewaal
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

Two Project Manager Agent Features You Might Like
Articles
5 min read

Two Project Manager Agent Features You Might Like

Discover two game-changing features of Microsoft’s Project Manager Agent including agent-to-agent communication and the new integrated interface in Planner.

E
Erik van Hurck
about 1 month ago
Read
Master Dependency Analysis in Microsoft Project with SSI Tools!
Articles
2 min read

Master Dependency Analysis in Microsoft Project with SSI Tools!

Learn how to master dependency analysis in Microsoft Project using SSI Tools’ Directional Path, Connecting Path, and Dependency Tracer to analyze predecessors, successors, and project logic.

K
Kenny Arnold
about 1 month ago
Read
A PM’s Halloween Survival Guide
Articles
5 min read

A PM’s Halloween Survival Guide

Discover the spooky parallels between Halloween and project management, from scope creep monsters to ghosted team members, in this fun survival guide for PMs.

R
Ronald B. Smith, MBA, PMP
about 2 months ago
Read
Explore All Articles