Back to ArticlesBack

Join 50,000+ PM Professionals

Get expert PM insights, PMP prep tips, and earn PDUs with exclusive content delivered weekly.

Protected by reCAPTCHA: Privacy & Terms

MPUG - Master Project User GroupMPUG

Default Formatting

As you are probably already aware, the default formatting of the Gantt Chart pane, which is shown on the right side of the Gantt Chart view, is as follows:

  • Detailed tasks are displayed with a light blue Gantt bar with the names of the assigned resources shown at the right end of the Gantt bar.
  • Milestone tasks are displayed as a black diamond with the Finish date of the task shown to the right of the milestone symbol.
  • Summary tasks are displayed as displayed as a black square bracket, with no text to the right of the summary task symbol.
  • Link lines are displayed with a “right angle” arrow from one end of the Predecessor task’s Gantt bar to one end of the Successor task’s Gantt bar. For example, when the dependency is Finish-to-Start, the link line is displayed from the Finish end of the Predecessor task’s Gantt bar to the Start end of the Successor task’s Gantt bar.

You can see the default formatting of the Gantt Chart pane in Figure 1.

Figure 1: Default Formatting of the Gantt Chart view

Formatting the Gantt Chart Pane

Microsoft Project offers you many ways to apply custom formatting to the Gantt Chart pane portion of the Gantt Chart view. For example, suppose that we want to format the Gantt Chart pane with the following requirements:

  • Display summary tasks as a green square bracket with the % Complete value shown to the right of the summary task symbol.
  • Display detailed tasks with a light green color, with the initials of the assigned resources shown above the Gantt bar, and the % Complete value shown to the right of the Gantt bar.
  • Display milestone symbols as a red diamond, with the Finish date shown to the left of the milestone symbol, and the % Complete value shown to the right of the milestone symbol.
  • Display link lines using a curved arrow rather than the “right angle” arrow.

To make the above formatting changes, we will need to take advantage of the power of the Bar Styles dialog, along with using an option that is available in the Layout dialog. The fastest way to access the Bar Styles dialog is to double-click anywhere in the white part of the Gantt Chart pane. You can also access the Bar Styles dialog by displaying the Format ribbon, clicking the Format pick list button in the Bar Styles section of the ribbon, and then selecting the Bar Styles item on the pick list. Using either method, Microsoft Project displays the default Bar Styles dialog shown in Figure 2.

Figure 2: Bar Styles dialog

The Bar Styles dialog displays a data grid that includes every symbol currently available in the applied view. For example, notice that the list includes items such as the Task, Split, Milestone, and Summary symbols. To the right of each symbol, the data grid includes columns with the instructions for how Microsoft Project will draw the symbol. For example, notice that the Task symbol is drawn from the Task Start date to the Task Finish date, as shown in the From and To columns for the Task item in the data grid.

At the bottom of the data grid, the Bar Styles dialog includes two additional formatting sections, and each section is displayed with its own worksheet tab. When you click the Bars tab, the Bars section includes the formatting instructions for the start, middle, and end portions of the symbol, including the color used for each portion. When you click the Text tab, the Text section shows what text to display at the left and right ends of the symbol, as well as on the top, bottom, and inside of the symbol.

Formatting Summary Tasks

To format the summary tasks according to our requirements, I will need to complete the following steps:

    1. Display the Bar Styles
    2. Select the Summary item in the data grid.
    3. In the Bars section of the dialog, change the Color value to Green for the Start, Middle, and End portions of the symbol, such as shown in Figure 3.

      Figure 3: Change the color of summary task Gantt bars

    4. Click the Text worksheet tab.
    5. In the Text section of the dialog, click the Right pick list and select the % Complete field, such as shown in Figure 4.

Figure 4: Change the text displayed for summary task Gantt bars

Formatting Detailed Tasks

To format the detailed tasks according to our requirements, I will need to complete the following steps:

    1. Select the Task item in the data grid.
    2. In the Bars section of the dialog, change the Color value to Green, Lighter 60% for only the Middle portion of the symbol, such as shown in Figure 5.

Figure 5: Change the color of detailed task Gantt bars

    1. Click the Text worksheet tab.
    2. In the Text section of the dialog, click the Right pick list and select the % Complete item, then click the Top pick list and select the Resource Initials item, such as shown in Figure 6.

Figure 6: Change the text displayed for detailed task Gantt bars

Formatting Milestone Tasks

To format the milestone tasks according to our requirements, I will need to complete the following steps:

      1. Select the Milestone item in the data grid.
      2. In the Bars section of the dialog, change the Color value to Red for only the Start portion of the symbol, such as shown in Figure 7.

Figure 7: Change the color of milestone task Gantt bars

      1. Click the Text worksheet tab.
      2. In the Text section of the dialog, click the Left pick list and select the Finish item, then click the Right pick list and select the % Complete item, such as shown in Figure 8.

Figure 8: Change the text displayed for milestone task Gantt bars

      1. Click the OK button to close the Bar Styles dialog and apply the new formatting to summary tasks, detailed tasks, and milestone tasks.

Formatting Link Lines

After applying the custom formatting to summary tasks, detailed tasks, and milestone tasks, I am ready to format the link lines by completing the following steps:

      1. Click the Format tab to display the Format
      2. In the Format section of the Format ribbon, click the Layout Microsoft Project displays the Layout dialog shown in Figure 9.

Figure 9: Layout dialog

      1. In the Layout dialog, select the second item in the Links section, as indicated in Figure 9 shown previously.
      2. Click the OK button when finished.

Figure 10 shows the Gantt Chart pane portion of the Gantt Chart view with all of the custom formatting applied.

Figure 10: Formatted Gantt Chart pane

Extra for Experts

To learn more about how the Bar Styles dialog controls the formatting of any Gantt-based view, apply a view such as the Tracking Gantt view, and then study each of the items shown in the data grid at the top of the Bar Styles dialog. For example, for the Tracking Gantt view, notice that Microsoft Project displays items like Critical, Critical Split, and Critical Progress at the top of the data grid. When you select the Critical item, notice that the Shape value is the “top half” Gantt bar. Select each of the items in the dialog and study the setup of the item, as shown on the Bars section of the dialog. You can use information like this to create your own custom formatting of Gantt bars in any Gantt-based view.

Get Weekly PM Insights

Join 50,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

Protected by reCAPTCHA: Privacy & Terms

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM GlossaryOur Faculty

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUGMaster Project User Group

© 2026 MPUG. All rights reserved.

TermsPrivacySitemapAdvertise
Articles

Fun with Formatting of the Gantt Chart View

Default Formatting As you are probably already aware, the default formatting of the Gantt Chart pane, which is shown on the right side of the Gantt Chart view, is as […]

6 min read
•over 5 years ago•Updated 10 months ago•
D
Dale HowardAuthor
Project Management
Microsoft Project
Best Practices
Productivity
D
Dale Howard

Content Writer

Dale Howard is currently a Senior PPM Consultant with Arch Systems, Inc. His hair and beard have turned white because of using Microsoft's project management tools for more than 20 years. Dale started his career using Microsoft Project 4.0 for Windows 95 and began using Microsoft's PPM tools when they introduced Project Central in 2000. Dale is the co-author of 23 books in Microsoft Project, Project Server, and Project Online. He is currently one 0f 26 Microsoft Project MVPs in the entire world and one of only 4 Project MVPs in the United states.

View all articles by Dale Howard
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

A PM’s Halloween Survival Guide: The Sequel You Didn’t Want but Definitely Need
Articles
1 min read

A PM’s Halloween Survival Guide: The Sequel You Didn’t Want but Definitely Need

Part II of the PM Halloween survival guide takes on shape-shifting requirements and dependencies that won’t stay resolved, with practical defenses for each.

A
Anonymous
18 days ago
Read
Context Engineering for Project Managers: Give AI the Project, Not Just the Question
Articles
1 min read

Context Engineering for Project Managers: Give AI the Project, Not Just the Question

Learn how to choose, date, and source the project information you give AI, so its risk analyses, status reports, and change request reviews reflect your actual project.

A
Anonymous
27 days ago
Read
The Climbing Rope – Why Projects Rise or Fall Together
Articles
1 min read

The Climbing Rope – Why Projects Rise or Fall Together

Ronald B. Smith uses a climbing rope to show how project team dynamics like trust, communication, and shared accountability decide who reaches the summit.

A
Anonymous
about 1 month ago
Read
Explore All Articles