Why is this task marked as critical?

Home Forums Discussion Forum Why is this task marked as critical?

Tagged: 

Viewing 2 reply threads
  • Author
    Posts
    • #418473
      Dan Schaeffer
      Participant

      I’m looking at a task in my schedule which is considered critical by MSP Pro 2016 but I cannot see why. The task has two successors, neither of which are marked critical (though the Gantt arrows which lead to them are red) and neither of them have successors.

      Any hints?

      Thanks,
      Dan

    • #418477
      Carlos Santos
      Guest
    • #418479
      Thomas Boyle
      Guest

      Dan,
      Does the task inspector tell you anything about the task?

      MSP sets the Critical flag based on total slack (default: TS<=0 is Critical.) There are three main causes for what you describe:
      1. Traditionally most common: The critical-marked task has an unmet deadline or constraint.
      2. Least common: The task’s dates are controlled by assigned resources whose working calendars are not well aligned with the project calendar.
      3. New common: The incomplete task has an out-of-sequence successor; i.e. the successor has an actual start that violates the relationship. (I first wrote about this for MSP 2016, but it may have started with 2013.) Good luck, tom

Viewing 2 reply threads
  • You must be logged in to reply to this topic.