Home › Forums › Discussion Forum › What causes these micro-overallocations in a Microsoft template schedule?
Tagged: leveling
I created a new project from the Software Development template and changed the units for 3 tasks from 100% to 200% for these 3 tasks
Auto-leveling leaves me with an overallocation because the first task is allocated for 8 hours and the second task is allocated for 0.01 hours. Any idea why this is happening and how to prevent it?
Thanks,
Dan Schaeffer