Undo Text Format

Home Forums Discussion Forum Undo Text Format

Tagged: 

  • This topic has 3 replies, 3 voices, and was last updated 9 years ago by Mark Sprinkle.
Viewing 3 reply threads
  • Author
    Posts
    • #400620
      Mark Sprinkle
      Participant

      Text format for a task was changed (e.g. text color was changed from default black to green). Now the text color won’t change when the task becomes critical. It seems like a change in text overrides the conditional formatting used for Text Styles.
      I would like to undo the task text format changes, go to the default format and allow Text Styles to format task formats.
      Any suggestions? I think what I want to do is undo any previous formats and go to a default condition.
      Thanks in advance for the help.
      Mark

    • #400622
      Mike P.
      Guest

      On the task ribbon choose “Clear” then “Clear Formatting”. Then, start over on the format ribbon “Format” then “Format Text Styles” to reset.

    • #400626
      Anonymous
      Inactive

      Mike, nice response (and simpler than what I was going to suggest). I do believe from the question that selecting all task and then Clear Formatting resets only the unique formatting. The text styles will stay applied.

    • #400629
      Mark Sprinkle
      Guest

      Perfect- that worked. Its so simple when you learn there’s a button to do exactly what one wants.
      Thanks Mike.