The bar wont follow to early date

Home Forums Discussion Forum The bar wont follow to early date

Viewing 4 reply threads
  • Author
    Posts
    • #415088
      Gamma Syahrial
      Guest

      Bar problem

      Hello i have some problem, like the picture
      when some task start earlier than plan, by input earlier date the bar in the gant chart dont follow into that earlier date. instead its show by point
      and when i input the actual duration the progres still show in the bar on gant chart not follow to earlier date
      i know i can correct this by changing the predecessor manualy

      all iam asking is there a way so the bar change automaticaly into the early date?
      thank you

    • #415089
      Gamma Syahrial
      Guest

      View post on imgur.com

      the picture wont show in first post

    • #415090
      Sai Prasad
      Spectator

      The dots appear on task 2 and 3 because the task was split or delayed to start later. To fix this issue, change the duration of this task to 0 and change it back to the duration you wanted.

    • #415091
      Sai Prasad
      Spectator

      Take a look at this image – https://i.imgur.com/uU5qT3u.png

      I have come across scenarios where the user presses the insert key by mistake when scrolling across the dates on the right side of the Task usage view. When insert key is pressed, Project considers that the work needs to moved to the next working day and sets 0 hours. In this image, on Monday 18th March, and Tuesday 19th March i pressed insert key and so the work got moved to the next working day. To fix this issue, you can either reset the duration to 0 days and change it back, or select those days on the right side of the Task usage viewand press Delete button.

    • #415130
      Gamma Syahrial
      Guest

      Thank you sai prasad, but i found another solution, it on project option – schedule – uncheck split in progres task

Viewing 4 reply threads
  • You must be logged in to reply to this topic.