Task with updated resource hours not feeding through to timesheet

Home Forums Discussion Forum Task with updated resource hours not feeding through to timesheet

Viewing 0 reply threads
  • Author
    Posts
    • #5281

      I have a project plan containing a task on which a resource was assigned 180h of Work. The resource completes her timesheet on a weekly basis and last week exceeded the Work by 2.5h (therefore zero Remaining Work for her on this task) and her Finish date on the task was reached, though the Finish date for the task itself is not until January 2013. This week the task was not appearing on her timesheet but as she still needs to do more work on this task she requested that it be ‘added back in’. I updated her resource allocation on this task via MS Project with a revised Finish date for her resource allocation of early December and adjusted Work so that she has 20h Remaining Work. I published the plan but the task has failed to reappear on her timesheet. To try and find where the problem lies I have added myself to the same task and it appeared on my timesheet. I have also tried adding the resource in question to another task in another plan and that appeared on her timesheet.

      Thanks in advance for your help.

Viewing 0 reply threads
  • You must be logged in to reply to this topic.