      Hi All,

      I hope that at least one of you can help me. I have done a construction programme and have used the flags to auto colour task under resource name. This has worked well and makes my projects much clearer to read but I have an issue when it comes to reporting.

      When I set the task completion to anything the bar that runs through the task is not visible. I have tried changing the bar style associated with that resource(flag) to not solid but still nothing.

      This has become a big issue when I’ve put the dropline on as we are behind in 1 area but ahead everywhere else and that is not visible.

      Please help…