Resource Loading

Home Forums Discussion Forum Resource Loading

Viewing 1 reply thread
  • Author
    Posts
    • #411649
      Timia Harris
      Member

      Is there a way to view each individual’s hours by WP? I tried creating a new group by WP, then by resource but it won’t group individually. Anyone have a solution?

    • #411659
      Sai Prasad
      Spectator

      Timia – Change the view to Task Usage and apply the group created.