Resource Group sample?

Home Forums Discussion Forum Resource Group sample?

Viewing 1 reply thread
  • Author
    Posts
    • #29497
      Subbu
      Guest

      Hi,

      Can someone share any example of how Resource Group field is used in MS Project 2013?

      Thanks

      Subbu

    • #29520
      Sai Prasad
      Spectator

      Subbu,

      Welcome to MPUG Discussion Forum!! Resource Group field is a free-form text field. If you want to group the resources by skillset, billable, then enter this information in the Group field in Resource Sheet.

      You can then use this resource group field in Filters/Groups/Highlight resources using the View ribbon.

      Hope this helps.

       

Viewing 1 reply thread
  • You must be logged in to reply to this topic.