      What is an easy way to report on the combined status of multiple projects that have the same design?

       

      The files could be set-up as a master with subprojects.

       

      The projects have the same tasks and outline.

    • #7092

      If you combine them into a Master project (be cautious of the links) you could consider showing the Project Summary task (in tools/ options in 2003 /07). Another option to consider is grouping by project – there is a column that displays project name.