Removing dates from gantt bars in MS Project

Home Forums Discussion Forum Removing dates from gantt bars in MS Project

Tagged: 

Viewing 5 reply threads
  • Author
    Posts
    • #23811
      Eran Frenkel
      Guest

      In my current project all tasks dates appear right of the bars in the Gantt chart. I know how to change the dates format, but I cannot figure out how to remove the dates completely.
      Can Someone help?
      Thanks,
      Eran

    • #23847
      Sai Prasad
      Spectator

      Hi Eran,

      Yes, it is possible.

      In Project 2010/Project 2013, select the Format tab. Select Format … Bar Styles in Bar Styles group. In the Bar Styles dialog, choose the row for which you want the date to be removed. Select the Text tab in Bar Styles and remove the date field from Right.

      In earlier versions, you select Format menu and repeat the process.

      Hope this helps.

    • #23852
      Eran Frenkel
      Guest

      Sai,
      It worked! Thank you very much!

    • #23918
      Sai Prasad
      Spectator

      You are welcome. I am glad to hear your problem is solved, Sai

    • #411819
      Mark Lima
      Guest

      Eran
      A great question which I was also puzzled by and to which many folk on the web have suggested lousy workarounds to.

      Sai
      Brilliantly concise and perfectly practical solution to achieve a process schedule not tied down to a specific start date when coupled with a week only calendar display. Many thanks 🙂

    • #411955
      Chethan Katarki
      Guest

      How to Remove the deadline for a task in project professional 2013.