Question Posted on another platform : How do i se Baseline % Complete!?

Home Forums Discussion Forum Question Posted on another platform : How do i se Baseline % Complete!?

Viewing 0 reply threads
  • Author
    Posts
    • #540835
      Duncan Matthews
      Participant

      Hello everyone. I hope y’all are doing good.

      As the title reads how do i show the baseline progress? I want to compare it with my actual progress.

      I set the baseline1 and then under activity details checked ‘actual’ and then added a column ‘% progress’ and updated each activity with some percentage.

      I can see the overall project progress but that is the actual progress. How do i compare it with the baseline progress? I have put baseline start and finish columns but i don’t find % baseline progress column?

      Am i doing something wrong? I use P6 so i don’t really know much about msp.

      Any help would be appreciated. TIA

      Note: i have not put any resources do i need to assign resources? but then it would be similar workflow to P6. How does msp make my work easier?

Viewing 0 reply threads
  • You must be logged in to reply to this topic.