Problem Modifying Row Height in Tracking Gantt view table

Home Forums Discussion Forum Problem Modifying Row Height in Tracking Gantt view table

Viewing 2 reply threads
  • Author
    Posts
    • #4948
      In the attached file, I have been trying to adjust the row height in the Tracking Gantt chart view to be smaller, like it is in the Gantt Chart view.  I have not been successful in making this happen.  Any suggestions anyone?
      I am using MS Project 2007 Professional.
    • #6291
      Regina, I have found that the bar type text, when added to the top or bottom of the bar, causes the overall row height to expand. I think you have a number of text fields selected to be placed on the top of the bar.
    • #10006
      Hello –
      Row height cannot less the height of the bars displayed. Choose Format, Barstyles and in Text tab, remove/reorder the fields displayed.
      Hope this helps
      — Sai, MCTS Project
Viewing 2 reply threads
  • You must be logged in to reply to this topic.