Printing the Timeline and Tracking Gantt views simultaneously

Home Forums Discussion Forum Printing the Timeline and Tracking Gantt views simultaneously

Viewing 2 reply threads
  • Author
    Posts
    • #93692
      Jeffrey Thompson
      Participant

      Hi,
      Does anyone know how to print the Timeline and Tracking Gantt views simultaneously?
      I look forward to your thoughts.

      Regards,

      Jeffrey

    • #96858
      Sai Prasad
      Spectator

      Hi Jeffrey,

      Timeline and Tracking Gantt are two separate views. You can print only one view at a time. I suggest select the Timeline and use Copy Timeline button in Format to copy for presentation, and then paste this image in paint brush application. Then, select Gantt Chart and use Copy Picture option in Task ribbon and then paste this image below the previous image. Print the final image to the printer

      Hope this helps

    • #476673
      Bob Cunningham
      Participant

      Alternatively you should be able to take a screenshot of the timeline and use that image in the header (or footer) of the printout. Unfortunately that would have to be done manually every time you would like to print. However if your printout is more than one page it will show again on all subsequent pages.

Viewing 2 reply threads
  • You must be logged in to reply to this topic.