Lag and elapsed time

Home Forums Discussion Forum Lag and elapsed time

Viewing 4 reply threads
  • Author
    Posts
    • #403706

      Using Project 2016. In the Task Information box, enter a Lag of -50%. MSP keeps adding an “e” and assume for elapsed time.
      Back on the Entry table, in the predecessor column, can edit out the “e” or just type it out.
      Is this a new feature (yuck), a problem with the Task Information box or do I need to change an overall function someplace else?
      Thank you, Betty

    • #403707
      Jigs Gaton
      Participant

      Hi there Betty, I am not seeing that here. In the Predecessor Entry table, Lag column, it just shows -50% and the task seems to calculate correctly. Hmmm…

    • #403710
      Anonymous
      Inactive

      Betty, I am getting the same behavior you are. Strange. I don’t use that kind of predecessor very often but never had the e entered automatically. I’m using Project Pro for O365. That does NOT happen on my Project 2010 version. Not sure what or when that happened, or if this is a bug or by design. Sorry for the lack of a good answer.

    • #404037
      Sai Prasad
      Spectator

      This is definitely a BUG and not default behavior in Project 2016. This is reported to Microsoft and you should expect it to be fixed in the next update. Till that time, remove the “e” from the predecessor.

    • #404052
      Betty Boushey
      Guest

      Thank you! It is always nice to know it is a bug and a solution in the works! Made my day!93