Insert Subprojects, Project 2016

Home Forums Discussion Forum Insert Subprojects, Project 2016

  • This topic has 1 reply, 2 voices, and was last updated 7 years ago by Josh Logan.
Viewing 1 reply thread
  • Author
    Posts
    • #412306
      Anonymous
      Inactive

      I have a master project withe 100 activities/tasks with a milestone task of conclusion.

      Later i insert a small subproject (5 tasks)

      I would like to have dependencies between the last tak of my master project and my subproject summary task.

      Then if i track the tasks of master project will have automatically inpact on the subproject inserted.

      Other way How can i constraint (start and finish) the subproject with the master project?

    • #412518
      Josh Logan
      Guest

      Carlos –

      Insert the sub-project, then create the dependency links between the master project’s tasks and the sub-project’s tasks

      Ideally, maintain the sub-project as linked, to the master project (make updates to the linked version of the sub-project); otherwise, the links may go away if you delete/re-add a modified sub-project.

      To create the link:

      1) Select the predecessor task
      2) Hold the CTRL key
      3) Select the successor task and release the CTRL key
      4) Press the “link the selected tasks button” key (Ctrl + F2) in the Task Menu.

Viewing 1 reply thread
  • You must be logged in to reply to this topic.