How to insert extra column in the table in Gantt view to display the period?

Home Forums Discussion Forum How to insert extra column in the table in Gantt view to display the period?

Tagged: , ,

Viewing 1 reply thread
  • Author
    Posts
    • #5170

      I’m trying to find out if there is a way of inserting an extra column in the table in Gantt view to display the period. Eg Period 1, 2 etc. For instance if I have a task which starts on 5 April I would want Period 1 to show. Our periods start from 5 April and the next period is 4 weeks after the previous one. Hope someone can help!

       

    • #6863

      Hello Anita,

      Creating a group listing at 4-week intervals starting from a specified date may work in your case. Ellen Lehnert has an article on grouping here at https://www.lehnertcs.com/pdfs/20080125_213649_tip.pdf

      Regards.

       