      Hello I have a Hammock task and I did not add it to the schedule.
      However every task that I add to the schedule starts on 9/3 but the project start date is 8/6

      How do I remove this. I can’t find it in the schedule

    • #5197

      Hello Amanda,

      If you can send me the schedule at projectuser-at-fastmail.fm, I can take a look at it and post back on what I see.

      Regards

    • #6908

      A number of things can cause this.  Check that you haven’t assigned any predecessors or successors or constraints to any of your Summary Lines.  Next, check your “Status” date by going to “Project”, “Project Information”.  Another possible but unlikely cause is your project calendar or your resource calendar or task calendar.  If none of these is the cause, email me your file and I’ll check out some other possibilities.

       

      Roy    roy.pool@siemens.com

    • #9806

      Have you checked Project Information , START DATE? The date automatically sets the date for a new task until a predecessor is assigned.