Home › Forums › Discussion Forum › Fiscal Years in Visual Reports
Tagged: fiscal years, Microsoft Project 2010, reports
Hello,
I configured MSP 2010 to use my client’s fiscal year (I added “FY starts in:” in “options” and added “Use FY” in the timeline configuration). The Gantt chart, resource usage, etc. look okay in the application. However, when I use Visual Reports to create cash flows, resource allocation charts, etc., it displays calendar years. Is there a way to fix this? It is a real problem, as all of the project reporting is coming via visual reports and calendar year is not acceptable to my client.
Any help is greatly appreciated.
Thanks,
– Steve