Error with inactivating tasks with 0% complete

Home Forums Discussion Forum Error with inactivating tasks with 0% complete

Viewing 1 reply thread
  • Author
    Posts
    • #36280
      Jeffrey Thompson
      Participant

      Hi

      I hope you are having a great day. I am experiencing an error message when I attempt to inactive some tasks that have 0% complete. Have you experienced this error before?

      I look forward to your thoughts.
       

      Regards,

       
      Jeffrey

    • #77601
      Sai Prasad
      Spectator

      I doubt your question is Project displays error when inactivating in progress tasks or completed tasks – see https://i.imgur.com/zoAJeUS.png. This is usual, as in progress tasks can be cancelled rather reset the remaining work of the task to 0. If you are receiving an error message even for 0% tasks it looks peculiar. Can you throw more light on its predecessor/successor % completion or send a screenshot of the error message with the portion of the file