    • #300886

      Hello

      I would like to be able to create a specific fiscal calendar in MSPS 2010 (E.g.: Jan start on Dec 20 previous year to Jan 23 current year, Feb starts Jan 24 and ends on Feb 20, etc.).
      This calendar would allow me to create project reporting based on this fiscal calendar. E.g. monthly cost based on fiscal month, or hours (which may be translated in Full Time Employee -FTE-) required per month for a specific project or a group of projects.
      How can I create such calendar and how can I use it in the reporting examples above?

      Thank you very much

      Chantal

    • #301273
      Sai Prasad
      Spectator

      Chantal – Project uses Gregorian Calendar to define the months of the year and this cannot be changed.

    • #301667

      Hello Sai

      Thank you for your quick answer. I understand Will continue to use to export the data in excel and redistribute it as per our fiscal calendar dates.

      Thanks again

      Chantal