Home › Forums › Discussion Forum › Baseline Gantt bars not aligning to recently baselined project
I’ve noticed that when I baseline a project schedule and immediately switch to the Tracking Gantt view, the baseline gantt bars do not align with the then-current start and finish bars. The key is that I just did the baseline. What I’ve found is that this occurs when I use the default date format of ‘Mon 10/1/12’.
If I change the date format display to include the hours and minutes, the baseline bars correct themselves (below). Why is this happening?