Reply To: Project Server 2007 Resource % allocated to a Task Changing

Home Forums Discussion Forum Project Server 2007 Resource % allocated to a Task Changing Reply To: Project Server 2007 Resource % allocated to a Task Changing

#6440
Richard,
You may have figured this out but it’s the same answer as described below.  The Units column on the task form represents Assignment Units.
Larry Christofaro