Back to ArticlesBack

Join 50,000+ PM Professionals

Get expert PM insights, PMP prep tips, and earn PDUs with exclusive content delivered weekly.

MPUG

Project Risk Analysis

There are two important outcomes for most projects beyond the obvious scope and quality objectives: Cost and Schedule.

The cost outcome directly affects the value of performing the project in terms of profit and loss.  The schedule outcome also affects cost and has other less tangible impacts such as loss of reputation caused by late delivery.

Cost Risk Analysis

Many organizations focus on cost risk when producing proposals. Unfortunately the primary reason for this is because it is perceived as quick and easy.  The scope of work will often be estimated at a high level as a series of line items in a spreadsheet.  This lends itself to easily adding in overheads, profit and contingency as percentages to arrive at a price.

There are several techniques for performing “risk analysis” on the cost data including proprietary risk analysis packages through home-grown macros.  Many of these cost risk solutions even employ sophisticated algorithms like Monte Carlo simulation, though this is not really necessary because cost risk analysis can easily be done analytically.

Unfortunately this approach has many pitfalls, chief among them that the cost impact of potential schedule delays cannot be easily assessed.

Schedule Risk Analysis

Schedule risk analysis will not only provide information regarding expected completion dates but it can also produce a more realistic assessment of likely project costs.  So why do so many organizations still produce unrealistic proposals based purely on cost risk? This is largely because of the perceived effort. The irony is that many of these same organization will have also produced a schedule to determine a date to include in their proposal.

Resource/Cost loading a schedule is no more arduous than creating a spreadsheet to model costs although it does require the dissolving of the ‘silos’ that so often separate cost and planning in many organizations.

Monte Carlo simulation on a schedule doesn’t have to be onerous.  If uncertainty data is available for cost estimates then often the same data can be used in the schedule.

Performing a Schedule Risk Analysis as part of the proposal process will avoid the pitfall of only discovering a low probability of schedule success after the contract has been awarded.

The Benefit of Cost/Schedule Risk Analysis vs simple Cost Risk Analysis

Cost risk analysis tends to treat each component of the estimate in isolation. Even if correlation or ‘drivers’ are used to create shared influencing factors the mean (expected) cost will often remain similar even if the range (deviation) of the results changes.  Schedule risk analysis on the other hand, assuming appropriate predecessor/successor logic is in place, can additionally produce more realistic forecasts taking into account merge bias and rate changes.

Summary

Schedule Risk Analysis when producing proposals can be an easy way to ensure commitments are realistic and improve chances of success while reducing project costs by focusing on the things that matter.  Embracing risk can improve confidence and ultimately profitability.

barbecana info

Get Weekly PM Insights

Join 50,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM Glossary

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUG Logo

© 2026 MPUG. All rights reserved.

TermsPrivacySitemap
Articles

Cost vs Schedule Risk Analysis for Proposals

  Project Risk Analysis There are two important outcomes for most projects beyond the obvious scope and quality objectives: Cost and Schedule. The cost outcome directly affects the value of […]

3 min read
•about 10 years ago••
T
The MPUG CommunityAuthor
Project Management
Microsoft Project
Best Practices
Productivity
T
The MPUG Community

Content Writer

MPUG has a global network of over 200,000 project management professionals across 170+ countries. For over 25 years, it has served as a premier platform fostering connection, knowledge sharing, and professional development within the project management community. MPUG champions the use of technology to optimize project management processes. It offers a comprehensive suite of resources and services, including live sessions, accredited training courses, informative lessons, industry articles, and interactive discussion forums. Committed to empowering its members to "Master Projects for Unlimited Growth," MPUG equips our members with the latest industry trends and propels their career advancement. Whether you're a budding project manager or a seasoned practitioner, MPUG provides an invaluable platform to hone your skills and bolster your project management expertise.

View all articles by The MPUG Community
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

Beyond Project Online: Why Now Is the Time to Plan Your Move to Modern Portfolio Management and How We Can Help
Articles
5 min read

Beyond Project Online: Why Now Is the Time to Plan Your Move to Modern Portfolio Management and How We Can Help

Microsoft Project Online retires September 2026. Learn why now is the time to plan your transition to modern portfolio management and join our free webinar on January 28.

T
The MPUG Community
about 12 hours ago
Read
Two Project Manager Agent Features You Might Like
Articles
5 min read

Two Project Manager Agent Features You Might Like

Discover two game-changing features of Microsoft’s Project Manager Agent including agent-to-agent communication and the new integrated interface in Planner.

E
Erik van Hurck
about 2 months ago
Read
Master Dependency Analysis in Microsoft Project with SSI Tools!
Articles
2 min read

Master Dependency Analysis in Microsoft Project with SSI Tools!

Learn how to master dependency analysis in Microsoft Project using SSI Tools’ Directional Path, Connecting Path, and Dependency Tracer to analyze predecessors, successors, and project logic.

K
Kenny Arnold
2 months ago
Read
Explore All Articles