Back to ArticlesBack

Join 50,000+ PM Professionals

Get expert PM insights, PMP prep tips, and earn PDUs with exclusive content delivered weekly.

MPUG - Master Project User GroupMPUG - Master Project User Group

Barbara from Denver, CO asks: I want to used earned value calculations to help manage my projects. However, when I look at the BCWS and BCWP fields, the data doesn’t seem to be calculated. What’s going on?

Answer: Earned value can be a very helpful indicator of the health of your project. It’s the equalizer between duration and work in evaluating project performance. For instance, did you do the work you planned to perform in the timeframe you planned to perform it? Did the work cost you more (more time) than you planned and how does that relate to the schedule?. Earned Value is complicated and can’t be addressed fully in this article. However, I would like to address the question above.

Earned value calculations need several values to be able to calculate. If something’s missing or awry, the earned value function won’t work.

  • If you’re not using costs (a value in the standard cost field on the Resource Sheet), earned value won’t calculate. Most of the Microsoft Project earned value calcuations are using the cost values calculated per task.
  • The accuracy of assignments on tasks will influence the accuracy of calculations (correct number of hours = correct costs).
  • If resource calculators aren’t up to date, resource assigments won’t be accurate because resources are scheduled based on availability.
  • Most of the earned value calculations also are looking for initial schedule values. This means if you don’t have a baseline set, you won’t see earned value.
  • Earned value will also be calculated based on a specific status in time. Therefore, the status date must be set or earned value won’t calculate.
  • Track the project — actuals must be entered.
  • Uncompleted work has to be rescheduled in order to keep the schedule accurate for the future calculations.

In the earned value table below I set the baseline for this short project. Go to View | Table | More Tables | Earned Value.

Figure 1. A sample project to demonstrate earned value.

Ask the Teacher: Earned Value Doesn’t Want to Calculate

For this example, the project started on September. 1, 2008. Note that there are only values in EAC (Estimate at Completion) and BAC (Budget at Completion), which is actually the baseline cost. Also note that the values are matching at this time. When I pointed to the EV (earned value) field, the option popped up to get help for a field. This is a wonderful place to see in detail how a field is actually being calculated. I also encourage you to see the calculations for each of the fields so you understand how they work before you start to depend on them for project forecasting.

Now I’ll enter some actual values as work performed on tasks. Tasks 3 and 4 are marked completed later than scheduled. Task 5 is 50% complete. The remaining work was increased by three days also. After the tracking information was entered, there was no change to the EV table. I then entered a status date of September 14, 2008 at Project | Project Information | Status Date | OK. Figure 2 shows the result.

Figure 2. The sample project showing updated values after modifying the status date.

Ask the Teacher: Earned Value Doesn’t Want to Calculate

As you can see, values have been updated in all of the fields.

There are also two other standard EV tables called Earned Value Schedule Indicators and Earned Value Cost Indicators. There’s an option to use physical percent complete (Tools | Options | Calculations | Earned Value) for these calculations instead of the default of duration percent complete. In this same dialog for options you can also select an alternate baseline to be used for the EV calculation. The physical percent complete would allow you to post a percentage instead of using the pre-calculated percentage. Physical Percent complete is available on the Tracking table or may be inserted into any table as needed.

Get Weekly PM Insights

Join 50,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM Glossary

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUG Logo

© 2026 MPUG. All rights reserved.

TermsPrivacySitemap
Articles

Ask the Teacher: Earned Value Doesn’t Want to Calculate

Barbara from Denver, CO asks: I want to used earned value calculations to help manage my projects. However, when I look at the BCWS and BCWP fields, the data doesn’t […]

3 min read
•over 17 years ago•Updated 13 days ago•
E
Ellen LehnertAuthor
Project Management
Microsoft Project
Best Practices
Productivity
E
Ellen Lehnert

Content Writer

Ellen Lehnert, PMP, Microsoft Project MVP, MCP, is a independent consultant and trainer on Microsoft Project and Project Server. She has taught Microsoft Project over 400 times and is the author of  MS Project 2010 and 2013 published courseware. Ellen is also a contributor and tech editor for many reference books, a developer for the Microsoft Project certification tests and is a frequent meeting speaker for Microsoft, MPUG and PMI. Contact Ellen at ellen@lehnertcs.com.

View all articles by Ellen Lehnert
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

How Reserves Keep Projects Alive
Articles
4 min read

How Reserves Keep Projects Alive

Learn how project reserves protect your budget and schedule from unexpected risks, including when and how to use contingency, management, schedule, and cost reserves effectively.

R
Ronald B. Smith, MBA, PMP
9 days ago
Read
Why Platform Migrations Fail (And How to Land Yours Successfully)
Articles
4 min read

Why Platform Migrations Fail (And How to Land Yours Successfully)

Learn why platform migrations fail and how to land yours successfully using proven change management tactics for PMOs facing tool transitions like Project Online’s retirement.

T
The MPUG Community
12 days ago
Read
Beyond Project Online: Why Now Is the Time to Plan Your Move to Modern Portfolio Management and How We Can Help
Articles
5 min read

Beyond Project Online: Why Now Is the Time to Plan Your Move to Modern Portfolio Management and How We Can Help

Microsoft Project Online retires September 2026. Learn why now is the time to plan your transition to modern portfolio management and join our free webinar on January 28.

T
The MPUG Community
23 days ago
Explore All Articles
Read