Angelo A asks: “Your mission, should you choose to accept it, is to find within Microsoft Project a cumulative resource graph over time, representing the total headcount (in total hours) of manpower (FTE or EQP) across a given project. To add to your troubles, there are resources that aren’t resources, namely the subcontract, travel, equipment numbers that are thrown in and will need to be filtered back out of the totals. A labor histogram is what would work best for us.”

Answer: I will accept this mission and do my best to answer this question. The histogram that you are looking for can be found in the Resource Usage view. This view is by resource name and you will be looking at each resource individually. Below is a view showing the head count you’re looking for. On the graph it’s called Peak Units. This value may be looked as either in the decimal or percentage — the picture below is showing the decimal view and time density per month.
Ask the Teacher: Cumulative Resource Totals in a Histogram Format
Right clicking on the boxes to the right of Peak Units will give you options to change the data available in this view. The choices may also be reached through Format | Details when in this view. Below is the same view using the cumulated work option. It’s a way of seeing the work budget over time for a resource. Cumulated cost is also available.
Ask the Teacher: Cumulative Resource Totals in a Histogram Format
To handle the “other resources” that Angelo is looking for, I suggest a totals report using the resource sheet. To obtain the breakdown by category, create a custom column with the different subtotal levels that are needed. Then create a cost table with the columns that will be needed for the report. To get accumulated subtotals, create a grouping based on the custom category column. Below is this report shown in level 1 format. (Formatting toolbar | Show | Outline Level 1). The category column doesn’t have to be on the table to get the grouping for the report.
Ask the Teacher: Cumulative Resource Totals in a Histogram Format
Mission accomplished!

Get Weekly PM Insights

Join 500,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM Glossary

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUG Logo

© 2025 MPUG. All rights reserved.

TermsPrivacySitemap
Articles

Ask the Teacher: Cumulative Resource Totals in a Histogram Format

Angelo A asks: “Your mission, should you choose to accept it, is to find within Microsoft Project a cumulative resource graph over time, representing the total headcount (in total hours) […]

2 min read
•over 17 years ago••
E
Ellen LehnertAuthor
Project Management
Microsoft Project
Best Practices
Productivity
E
Ellen Lehnert

Content Writer

Ellen Lehnert, PMP, Microsoft Project MVP, MCP, is a independent consultant and trainer on Microsoft Project and Project Server. She has taught Microsoft Project over 400 times and is the author of  MS Project 2010 and 2013 published courseware. Ellen is also a contributor and tech editor for many reference books, a developer for the Microsoft Project certification tests and is a frequent meeting speaker for Microsoft, MPUG and PMI. Contact Ellen at ellen@lehnertcs.com.

View all articles by Ellen Lehnert
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

Two Project Manager Agent Features You Might Like
Articles
5 min read

Two Project Manager Agent Features You Might Like

Discover two game-changing features of Microsoft’s Project Manager Agent including agent-to-agent communication and the new integrated interface in Planner.

E
Erik van Hurck
about 1 month ago
Read
Master Dependency Analysis in Microsoft Project with SSI Tools!
Articles
2 min read

Master Dependency Analysis in Microsoft Project with SSI Tools!

Learn how to master dependency analysis in Microsoft Project using SSI Tools’ Directional Path, Connecting Path, and Dependency Tracer to analyze predecessors, successors, and project logic.

K
Kenny Arnold
about 1 month ago
Read
A PM’s Halloween Survival Guide
Articles
5 min read

A PM’s Halloween Survival Guide

Discover the spooky parallels between Halloween and project management, from scope creep monsters to ghosted team members, in this fun survival guide for PMs.

R
Ronald B. Smith, MBA, PMP
2 months ago
Read
Explore All Articles