Back to ArticlesBack

Join 50,000+ PM Professionals

Get expert PM insights, PMP prep tips, and earn PDUs with exclusive content delivered weekly.

Protected by reCAPTCHA: Privacy & Terms

MPUG - Master Project User GroupMPUG

Nancy asks, “I have been a project controller for about seven years. I have a problem that I cant figure out. My % Complete column has stopped calculating. Also, the Actual Duration and Remaining Duration are not being updated either. Actual Duration is always zero even though its well into the task. So Remaining Duration equals Duration. What would cause that?”

Answer: This one is really puzzling. After reviewing the MPP file sent, I wasn’t able to see why the % completed doesn’t calculate. I have checked the settings which, are all fine. Then I exported the project into an XML file and re-imported it ( just in case the schedule is corrupt); but this didn’t change the behavior (which is a bummer).

I’ve also noticed that some % completed updates actually work. Task 31, for example, works fine, but Task 3 doesn’t work at all in regards to the % complete. It seems that a combination of settings and corruption could create this effect. So here’s how I suggest you make it work. (I assume this isn’t a Project Server environment, but only an MPP file.)

1. Save the project as an XML file.
2. Open the XML file in Microsoft Project and create a new project.
3. Go to tools | option. Within the Calculate Tab select “Updating Task Status updates Resource Status.”
4. Save the project.

Nancy replies: “Well, thank goodness! It’s in a Project Server environment, so I skipped steps 1 and 2. It still worked. Thank you so much!”

Get Weekly PM Insights

Join 50,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

Protected by reCAPTCHA: Privacy & Terms

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM GlossaryOur Faculty

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUGMaster Project User Group

© 2026 MPUG. All rights reserved.

TermsPrivacySitemapAdvertise
Articles

Ask the Experts: When % Complete Won’t Calculate

Nancy asks, “I have been a project controller for about seven years. I have a problem that I cant figure out. My % Complete column has stopped calculating. Also, the […]

2 min read
•over 17 years ago•Updated 8 months ago•
M
Marc SoesterAuthor
Project Management
Microsoft Project
Best Practices
Productivity
M
Marc Soester

Content Writer

Marc Soester is the Managing Director of i-PMO, an organisation dedicated to successfully implement Microsoft's Enterprise Project Management (EPM) solution throughout Australia. Marc and his team have extensive expertise in the implementation of Microsoft Project Server and Portfolio Server as well as conducting training in Project. He has more then six years of experience implementing EPM solutions and is Australia's first and currently only Project MVP (Most Valuable Professional). You can contact him at marc.soester@i-pmo.com.au.

View all articles by Marc Soester
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

The Climbing Rope – Why Projects Rise or Fall Together
Articles
1 min read

The Climbing Rope – Why Projects Rise or Fall Together

Ronald B. Smith uses a climbing rope to show how project team dynamics like trust, communication, and shared accountability decide who reaches the summit.

A
Anonymous
4 days ago
Read
Asana AI Teammates Are Now Included in Paid Tiers — and Billed by Consumption After That
Articles
1 min read

Asana AI Teammates Are Now Included in Paid Tiers — and Billed by Consumption After That

MPUG Editorial · September 18, 2026 · ~4 min read · Category: PM Platforms From mid-September, Asana AI Teammates and the Dash assistant are included in the company’s paid Agentic […]

A
Anonymous
12 days ago
Read
Teams Google Calendar Sync Retires in October 2026: What Project Managers Need to Do
Articles
1 min read

Teams Google Calendar Sync Retires in October 2026: What Project Managers Need to Do

MPUG Editorial · September 15, 2026 · ~4 min read · Category: Microsoft Tooling Microsoft is retiring Teams Google Calendar sync in October 2026, and if your program spans both […]

A
Anonymous
16 days ago
Read
Explore All Articles