Greg from Omaha asks: In Microsoft Project 2007 the current activity reports all sound similar. What’s the difference between these reports?

Answer: When I look through the names of the report titles, I can understand your confusion. These reports are actually the same report with a different filter applied to each one. The reports are also the same reports that have been in the system for years, so this information is applicable to Project 2007, 2003, and some of the older versions as well.

To get to the reports in Project 2007, click on: Report | Reports. In earlier versions, click on: View | Reports.

The resulting screen is shown in Figure 1. This is the Project 2007 version. Earlier versions will have the same content, but will be in black and white. Double-click on the Current Activities option and the result will be below.

Figure 1. The Reports screen in Project 2007.

Ask the Experts: Making Sense of Current Activity Reports

Figure 2. The Current Activity reports.

Ask the Experts: Making Sense of Current Activity Reports

Each of the reports in Figure 2 uses a specific table that may be changed or customized if necessary.

Ask the Experts: Making Sense of Current Activity Reports
The following filters are applied to the reports.

Ask the Experts: Making Sense of Current Activity Reports

To make changes to the reports, click on the report type | Edit. Any changes to these reports will be saved with the project. You can change the tables and the filter, add totals, add scheduling information, sort on any column in the task tables, print notes, and apply formatting.

To alter the columns in the tables, go to View | tables | more tables. Select the table you wish to change and click Edit. After the changes are completed, click OK.

Custom reports may be created by selecting the Custom option on Figure 1. Then select the report, copy it, and change the name. These reports may be copied through the Organizer and kept for future use with Tools | Organizer.

Get Weekly PM Insights

Join 50,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

Protected by reCAPTCHA: Privacy & Terms

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM GlossaryOur Faculty

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUGMaster Project User Group

© 2026 MPUG. All rights reserved.

TermsPrivacySitemapAdvertise
Articles

Ask the Experts: Making Sense of Current Activity Reports

Greg from Omaha asks: In Microsoft Project 2007 the current activity reports all sound similar. What’s the difference between these reports? Answer: When I look through the names of the […]

2 min read
•over 16 years ago•Updated 10 months ago•
E
Ellen LehnertAuthor
Project Management
Microsoft Project
Best Practices
Productivity
E
Ellen Lehnert

Content Writer

Ellen Lehnert, PMP, Microsoft Project MVP, MCP, is a independent consultant and trainer on Microsoft Project and Project Server. She has taught Microsoft Project over 400 times and is the author of  MS Project 2010 and 2013 published courseware. Ellen is also a contributor and tech editor for many reference books, a developer for the Microsoft Project certification tests and is a frequent meeting speaker for Microsoft, MPUG and PMI. Contact Ellen at ellen@lehnertcs.com.

View all articles by Ellen Lehnert
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

Collaboration challenges in remote projects (and how to fix each one)
Articles
1 min read

Collaboration challenges in remote projects (and how to fix each one)

Discover 5 common remote project collaboration challenges, from knowledge silos to unclear ownership, and learn practical ways to keep teams aligned and work moving.

A
Anonymous
5 days ago
Read
An Introduction to the PMI Practice Standard for Scheduling Conformance Index
Articles
1 min read

An Introduction to the PMI Practice Standard for Scheduling Conformance Index

Learn how the Conformance Index in PMI’s Practice Standard for Scheduling scores a CPM schedule model, and how to assess its components in any scheduling tool.

A
Anonymous
16 days ago
Read
A PM’s Halloween Survival Guide: The Sequel You Didn’t Want but Definitely Need
Articles
1 min read

A PM’s Halloween Survival Guide: The Sequel You Didn’t Want but Definitely Need

Part II of the PM Halloween survival guide takes on shape-shifting requirements and dependencies that won’t stay resolved, with practical defenses for each.

A
Anonymous
about 1 month ago
Read
Explore All Articles