Ellen from Wheaton, IL asks: Why does Microsoft Project 2010 have some bothersome behavior?!

Answer: Like an old friend or co-worker that you spend many hours a day with, Microsoft Project brings both contentment and frustration to my world. And that’s no different with the latest version, Project 2010. As the year draws to a close, I thought I would take this opportunity to get off my chest some of the bothersome behavior of my old, long-time friend and co-worker.

Reports

When using the Reports function, after making changes to the Report specifications I tend to click on Print Preview to view the results. If the results aren’t what I expected, I close the Print Preview, make changes to the specifications, and view the results again. When I attempt this using Project 2010, I find that the Reports function has closed. This is truly bothersome behavior compared to the prior versions of Project, where I was able to close Print Preview, make changes, and try again!

Ribbon Bar

What used to take two clicks can now take up to five clicks. I find that adding “Scroll to Task” as well as other functions to the Quick Launch bar cuts down the clicking!

Task Usage and Resource Usage

Why do the hours appear so light, and why don’t we get an option to have them appear normally?

Ask the Experts: Bothersome Behavior of the New Version of My Old Friend

Autocomplete for Task and Resource Names

In Excel this option can be turned off. Why is it not an option to turn Autocomplete off in Project 2010?

Formatting the Gantt Chart View

Using the Format bar to add features to the Gantt Chart and change formatting is much easier. However, the only way the view can be reset back to the default values is to add the Gantt Chart Wizard to a ribbon bar and select the Standard option.

Also, Format_Duration, the macro to change the durations to the same value, which was part of the previous versions, isn’t included in Project 2010.(When some tasks are shown in days and others are shown in weeks, this macro allows you to change all formatting to the same “denomination.”)

Project 2010 is a fantastic leap over the prior versions of Project. Some of the new capabilities are a breath of fresh air, and I regularly recommend the upgrade to my students and clients. However, like a spouse who leaves the cap off the toothpaste and shoes where you can trip over them, at times my old software friend makes me just say, “Huh?”

I think I feel better now. Thanks for listening and have a wonderful holiday season!

Get Weekly PM Insights

Join 50,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

Protected by reCAPTCHA: Privacy & Terms

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM GlossaryOur Faculty

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUGMaster Project User Group

© 2026 MPUG. All rights reserved.

TermsPrivacySitemapAdvertise
Articles

Ask the Experts: Bothersome Behavior of the New Version of My Old Friend

Ellen from Wheaton, IL asks: Why does Microsoft Project 2010 have some bothersome behavior?! Answer: Like an old friend or co-worker that you spend many hours a day with, Microsoft […]

2 min read
•almost 16 years ago•Updated 10 months ago•
E
Ellen LehnertAuthor
Project Management
Microsoft Project
Best Practices
Productivity
E
Ellen Lehnert

Content Writer

Ellen Lehnert, PMP, Microsoft Project MVP, MCP, is a independent consultant and trainer on Microsoft Project and Project Server. She has taught Microsoft Project over 400 times and is the author of  MS Project 2010 and 2013 published courseware. Ellen is also a contributor and tech editor for many reference books, a developer for the Microsoft Project certification tests and is a frequent meeting speaker for Microsoft, MPUG and PMI. Contact Ellen at ellen@lehnertcs.com.

View all articles by Ellen Lehnert
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

Collaboration challenges in remote projects (and how to fix each one)
Articles
1 min read

Collaboration challenges in remote projects (and how to fix each one)

Discover 5 common remote project collaboration challenges, from knowledge silos to unclear ownership, and learn practical ways to keep teams aligned and work moving.

A
Anonymous
8 days ago
Read
An Introduction to the PMI Practice Standard for Scheduling Conformance Index
Articles
1 min read

An Introduction to the PMI Practice Standard for Scheduling Conformance Index

Learn how the Conformance Index in PMI’s Practice Standard for Scheduling scores a CPM schedule model, and how to assess its components in any scheduling tool.

A
Anonymous
19 days ago
Read
A PM’s Halloween Survival Guide: The Sequel You Didn’t Want but Definitely Need
Articles
1 min read

A PM’s Halloween Survival Guide: The Sequel You Didn’t Want but Definitely Need

Part II of the PM Halloween survival guide takes on shape-shifting requirements and dependencies that won’t stay resolved, with practical defenses for each.

A
Anonymous
about 1 month ago
Read
Explore All Articles