Back to ArticlesBack

Join 50,000+ PM Professionals

Get expert PM insights, PMP prep tips, and earn PDUs with exclusive content delivered weekly.

Protected by reCAPTCHA: Privacy & Terms

MPUG - Master Project User GroupMPUG - Master Project User Group

Adenor from Oakbrook, IL asks: I have a task in a schedule that must start after an unknown date and must end on a specific date. I’ve tried to enter a start and finish date on the task, but it doesn’t seem to be working for me. After the task starts, it’ll take nine days including weekends. How can Microsoft Project schedule this task for me?

Answer: Project can certainly do this for you. Let’s take your problem one step at a time.

First, the need for start and finish dates. Since you can’t enter both a start and a finish date on a task, you can enter a “start no earlier” date to push the task forward in time and deadline. This will give you the ability to start the task after some date in the future and have a target for the ending date of the task.

To enter these values and dates:

  1. Double click on the task.
  2. Select the Advanced tab.
  3. Enter the deadline date.
  4. Select the Start no Earlier than Constraint.
  5. Enter the constraint date. Choose a date sometime in the future when you think it might start.
  6. Click OK.

Figure 1 shows how it would look with both constraints applied to a task.

Figure 1. Setting a “start no earlier” date constraint.

Ask the Experts: Applying Two Constraints on One Task

In this example I’ve also changed the Gantt chart to show the start no earlier date below the Gantt bar for the task, the constraint type above, the finish date to the right, and the deadline date to the right of the deadline on the task.

To create this formatting, right-click on the Gantt bar for the task and select Format Bar, then select the settings you see in the form in Figure 2. Using this method you would make changes on a Gantt chart for a single task bar.

The deadline date was added by: Format | Bar styles | Deadline | Text (in the bottom part of the form) | Deadline | OK. This is a change that will affect all deadlines applied to this Gantt view.

If the date format isn’t what you would like, you can make changes in Format | Layout.

Figure 2. The Format Bar property dialog.

Ask the Experts: Applying Two Constraints on One Task

The second part of your question asks about showing the task as nine days in duration, including weekends. When duration is entered, the system looks at the project calendar and uses availability according to that calendar, usually set for business days, which doesn’t include weekends. This can be overridden so that the task will use the physical number of days — both working and non-working. This feature is called elapsed time. Enter the duration as “9 ed” instead of “9d” to have physical days counted. See the comparison example in Figure 3.

Figure 3. Entering an elapsed time to count physical days with “ed” instead of “d.”

Ask the Experts: Applying Two Constraints on One Task

When the task starts to execute, I would recommend entering the actual start date to see how it compares against the deadline date and moving it forward to reflect what actually occurred. Your goal will be to not let the end of the task cross the deadline.

My recommended steps for scheduling the task to fit your needs are:

  1. Enter a start no earlier constraint.
  2. Enter a deadline for the task.
  3. Enter the duration using elapsed time (9 ed) to get physical days.
  4. Enter the actual start date of the task.
  5. Make sure that the end of the task doesn’t cross the set deadline.

Get Weekly PM Insights

Join 50,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

Protected by reCAPTCHA: Privacy & Terms

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM Glossary

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUG Logo

© 2026 MPUG. All rights reserved.

TermsPrivacySitemapAdvertise
Articles

Ask the Experts: Applying Two Constraints on One Task

Adenor from Oakbrook, IL asks: I have a task in a schedule that must start after an unknown date and must end on a specific date. I’ve tried to enter […]

3 min read
•over 16 years ago•Updated about 2 months ago•
E
Ellen LehnertAuthor
Project Management
Microsoft Project
Best Practices
Productivity
E
Ellen Lehnert

Content Writer

Ellen Lehnert, PMP, Microsoft Project MVP, MCP, is a independent consultant and trainer on Microsoft Project and Project Server. She has taught Microsoft Project over 400 times and is the author of  MS Project 2010 and 2013 published courseware. Ellen is also a contributor and tech editor for many reference books, a developer for the Microsoft Project certification tests and is a frequent meeting speaker for Microsoft, MPUG and PMI. Contact Ellen at ellen@lehnertcs.com.

View all articles by Ellen Lehnert
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

Your Project Online Migration Questions, Answered: Key Takeaways from Ira Brown
Articles
1 min read

Your Project Online Migration Questions, Answered: Key Takeaways from Ira Brown

Ira Brown, president of Project Widgets, breaks down the four realistic migration paths, key deadlines, and a pre-migration inventory checklist to help your organization plan ahead of the September 2026 Project Online retirement.

A
Anonymous
9 days ago
Read
The Compass vs. The Clock: Why Direction Beats Deadlines in Project Management
Articles
1 min read

The Compass vs. The Clock: Why Direction Beats Deadlines in Project Management

Discover why setting clear project direction matters more than chasing deadlines, and how compass-guided leadership delivers real value in project management.

A
Anonymous
20 days ago
Read
The Scripts That Save Projects: What to Say When Everything Goes Wrong
Articles
1 min read

The Scripts That Save Projects: What to Say When Everything Goes Wrong

Learn word-for-word scripts for handling scope creep, missed deadlines, executive pushback, and team performance issues as a project manager.

A
Anonymous
21 days ago
Read
Explore All Articles