Back to ArticlesBack

Join 50,000+ PM Professionals

Get expert PM insights, PMP prep tips, and earn PDUs with exclusive content delivered weekly.

Protected by reCAPTCHA: Privacy & Terms

MPUG - Master Project User GroupMPUG

girl-1632836_1920Every so often I’m asked to reproduce a project management technique in Microsoft Project that isn’t a named feature in the software. Such is the case with “hammock” tasks.

A hammock task is a task that has a variable duration. The duration is controlled entirely by other tasks in another or the same project. The start and finish of the hammock is linked to the other tasks’ start or finish. The duration of the hammock is recalculated when the linking tasks change their dates.


Want more Do’s and Don’ts? Check out MPUG’s new book: Microsoft® Project Do’s and Don’ts!


Opinions about hammock tasks range from “Don’t do it!” to “Always drive your level of effort tasks with the technique.” It’s easy to set up a hammock task; but there are caveats that you need to know before using the technique in a production environment. I’ll cover some of those in this article as well.

A hammock task looks pretty inconspicuous:

Sam_Huffman_Hammock_tasks_figure_1

The task names point out their function. The start of the hammock is the paste linked start date from “Hammock Start Link,” which I’ve formatted in bold red in the figure above. The finish of the hammock is the paste linked finish date from “Hammock Finish Link” formatted in bold green. Note the indicators in the lower right of the hammock tasks date cells. These indicators are visual markers telling us the dates are linked.

I will double the duration of task #2. This forces a recalculation, and the duration of the hammock task is changed to six days. The calculation may take a few seconds, even on a very fast machine, so be patient.

Sam_Huffman_Hammock_tasks_figure_2

I wrote this article using Project Professional in Manual Schedule mode, with a resource assigned at half time. This worked well with a simple resource using the same calendar as the project and with no overallocations. It’s likely that I would have to manually resolve any task or resource scheduling issues in a more complicated project. This would be true regardless of the scheduling mode selected.

Now for some caveats:

  • Hammock tasks can be confusing to anyone reading your schedule. So include a note restating the purpose of the task. For example, is it to collect a level of effort for management resources? Synchronizing the project with other tasks or projects in a program schedule?
  • Paste links can be lost easily, so visit the task and its position in your schedule often.
  • Since a hammock task receives its dates as a paste link, the task probably shouldn’t have a predecessor or successor. If it’s necessary to link with other tasks, revisit your need for a hammock task. Maybe a normal task will meet your needs.
  • Hammock tasks are schedule-driven and not resource-driven. Be cautious when leveling resources. You might consider making the task a higher priority than other tasks so Project will skip the task when leveling the rest of the project.

There are always sequencing workarounds and alternatives, but the hammock task continues to be one of the primary tools used in scheduling. You can find more on this subject online and in MSDN. Use the term “hammock task” and you’ll get a great deal of information on the pros and cons of using a hammock task.

A version of this article originally appeared on Sam Huffman’s “Project Blog” here.

Image Source

Get Weekly PM Insights

Join 50,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

Protected by reCAPTCHA: Privacy & Terms

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM GlossaryOur Faculty

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUGMaster Project User Group

© 2026 MPUG. All rights reserved.

TermsPrivacySitemapAdvertise
Articles

Do’s and Don’ts: Using Hammock Tasks

Every so often I’m asked to reproduce a project management technique in Microsoft Project that isn’t a named feature in the software. Such is the case with “hammock” tasks. A […]

3 min read
•about 10 years ago•Updated 10 months ago•
S
Sam HuffmanAuthor
Project Management
Microsoft Project
Best Practices
Productivity
S
Sam Huffman

Content Writer

Sam Huffman first gained insight into Microsoft Project while working as a member of the MS Project development and support team. He has maintained his depth of knowledge of MS Project with each release and is a leading authority in the use and features of MS Project, Project Server and Project Online. Since the early 1990's Sam has honed his instruction skills by delivering training programs to thousands every year. Sam is a frequent content contributor to the Microsoft Project User Group (MPUG) and speaks to groups often about MS Project, Enterprise Project Management and the discipline of Project Management. He was awarded Microsoft Most Valuable Professional from 2010-2017. Check out his blog on MS Project. The softcover version of my newest book Microsoft® Project Do’s and Don’ts is now available for purchase! It is portable, brief and to the point so you can find help when you need it. Through tips, best practices and examples it will help you jumpstart your project!

View all articles by Sam Huffman
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

Collaboration challenges in remote projects (and how to fix each one)
Articles
1 min read

Collaboration challenges in remote projects (and how to fix each one)

Discover 5 common remote project collaboration challenges, from knowledge silos to unclear ownership, and learn practical ways to keep teams aligned and work moving.

A
Anonymous
2 days ago
Read
An Introduction to the PMI Practice Standard for Scheduling Conformance Index
Articles
1 min read

An Introduction to the PMI Practice Standard for Scheduling Conformance Index

Learn how the Conformance Index in PMI’s Practice Standard for Scheduling scores a CPM schedule model, and how to assess its components in any scheduling tool.

A
Anonymous
13 days ago
Read
A PM’s Halloween Survival Guide: The Sequel You Didn’t Want but Definitely Need
Articles
1 min read

A PM’s Halloween Survival Guide: The Sequel You Didn’t Want but Definitely Need

Part II of the PM Halloween survival guide takes on shape-shifting requirements and dependencies that won’t stay resolved, with practical defenses for each.

A
Anonymous
about 1 month ago
Read
Explore All Articles