Back to ArticlesBack

Join 50,000+ PM Professionals

Get expert PM insights, PMP prep tips, and earn PDUs with exclusive content delivered weekly.

Protected by reCAPTCHA: Privacy & Terms

MPUG - Master Project User GroupMPUG - Master Project User Group

We’ve all heard stories about estimation padding. The developer provided a 30 day estimation. His team lead doubted his wisdom and added another 10 days to it. The manager didn’t have a lot of trust in his teams abilities and added another 10 days. The senior executive felt more comfortable with the addition of another 10 days. The original 30 days doubled to 60 days by the time it reached the project sponsor/stakeholder. Their intentions were good; but the approach was based on rules of thumb (and maybe lack of documentation of the estimation details). The root cause behind all this is uncertainty and lack of confidence. If we can quantify the confidence or lack of confidence as a percentage, a more rational approach can be developed to add buffers to estimates.

If the project is in the initiation phase and the estimations are still based on high-level business requirements, a rule to add a certain percentage may be a good practice. Once the detailed requirements are being defined, the estimates need to be broken down to the task level. At this time, if out of 100 tasks, there’s no ambiguity or uncertainty on implementation of 80 tasks, it’s unnecessary to add a buffer to these 80 tasks. However, the remaining 20 tasks may need the addition of buffers in the estimation to account for the lack of confidence and ambiguities.

A rational approach would be to determine the specific time of buffer time needed for each of the 20 tasks. This sounds overwhelming but it’s not. I determine a confidence percentage for each task. If I’m 50 percent confident of the estimation for Task A, and I have an estimate of 10 days, I would need a five-day buffer to mitigate the risks.

It can be easily integrated into the project plan, in Microsoft Project. Add a new column of type “Number” in the Gantt chart and name it as Confidence %. Add two more columns, of type “Duration,” for the original estimates and the calculated estimate (Estimation with Confidence). This is required since Microsoft Project doesn’t allow the Duration column to be based on a formula. The formula can be added as in Figure 1. The calculation is simple: Add the percentage increase to the original estimate.

Figure 1. The addition of a calculated estimate in Microsoft Project.

A Rational Approach to Padding

The data from “Estimate (from Confidence)” will need to be copied to the Duration column.

This simple technique, while providing a rational way to add buffers, also helps in documenting the tasks in the project plan where there are some issues or risks. All the tasks that have confidence less than 100 percent must have associated issues or risks. These issues or risks must also be logged in issues or risks logs. As these issues or risks are resolved, the confidence for these tasks will increase. This should be reflected in a more accurate prediction of the project timelines and cost and better returns to the project sponsors and stakeholders.

An enhancement of this template could be to add another column listing the issue or risk log identifier. This could help with audit and reconciliation of risks and issues with the project plan. A task with Confidence percent less than 100 and a missing risk log identifier should raise a red flag.

One of my project management gurus once told me that project management isn’t easy — its supposed to be lot of work. It still remains lot of work. But, this technique has made it a little bit easier for me. While I continue working on adding the enhancements to my template, the approach has definitely helped me rationalize the estimate, risk mitigation and planning process as a whole.

A Rational Approach to Padding

Sumit Agarwal, PMP, currently works for Perot Systems, just outside of Philadelphia. He can be reached at sumitag@hotmail.com.

Get Weekly PM Insights

Join 50,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

Protected by reCAPTCHA: Privacy & Terms

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM Glossary

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUG Logo

© 2026 MPUG. All rights reserved.

TermsPrivacySitemapAdvertise
Articles

A Rational Approach to Padding

We’ve all heard stories about estimation padding. The developer provided a 30 day estimation. His team lead doubted his wisdom and added another 10 days to it. The manager didn’t […]

3 min read
•over 17 years ago•Updated about 2 months ago•
S
Sumit AgarwalAuthor
Project Management
Microsoft Project
Best Practices
Productivity
S
Sumit Agarwal

Content Writer

Sumit Agarwal, PMP, currently works for Perot Systems, just outside of Philadelphia. He can be reached at sumitag@hotmail.com.

View all articles by Sumit Agarwal
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

Your Project Online Migration Questions, Answered: Key Takeaways from Ira Brown
Articles
1 min read

Your Project Online Migration Questions, Answered: Key Takeaways from Ira Brown

Ira Brown, president of Project Widgets, breaks down the four realistic migration paths, key deadlines, and a pre-migration inventory checklist to help your organization plan ahead of the September 2026 Project Online retirement.

A
Anonymous
15 days ago
Read
The Compass vs. The Clock: Why Direction Beats Deadlines in Project Management
Articles
1 min read

The Compass vs. The Clock: Why Direction Beats Deadlines in Project Management

Discover why setting clear project direction matters more than chasing deadlines, and how compass-guided leadership delivers real value in project management.

A
Anonymous
26 days ago
Read
The Scripts That Save Projects: What to Say When Everything Goes Wrong
Articles
1 min read

The Scripts That Save Projects: What to Say When Everything Goes Wrong

Learn word-for-word scripts for handling scope creep, missed deadlines, executive pushback, and team performance issues as a project manager.

A
Anonymous
27 days ago
Read
Explore All Articles